JM2020-21 Thiruvananthapuram district Kulathoor GP providing pipe line extension and providing house hold connections in Kulathoor GP (phase 2)J

Project JM2020-21 Thiruvananthapuram district Kulathoor GP providing pipe line extension and providing house hold connections in Kulathoor GP (phase 2)J
Project Code TVMJJM08205576P1
Type Package
Main Project JJM 2020-21 Thiruvananthapuram District Kulathoor Grama Panchayath -Providing pipe line extension and providing household connections in Kulathoor Grama panchayath (Phase 2)
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JM2020-21 Thiruvananthapuram district Kulathoor GP providing pipe line extension and providing house hold connections in Kulathoor GP (phase 2)J
Status On-going
District Thiruvananthapuram
Executing Office Parassala WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 13900000
TS Number TS/2020-2021/2020/15397
Technical specification 1000 water connections can be provided by pipeline extensions after the augmentation of the scheme such as replacing of damaged pipelines and providing for house hold connections by conducting hydraulic feasibility survey for preparing distribution net work map (GIS),making soft drawings for further minor pipeline extensions in densely populated areas facing shortage of drinking water
Contractor DEVARAJ DEVADASAN (Mob: 9446811195)

Project Review

See All Review messages
Review Date Review Message Review Attended By
28 May 2021 the work is delayed due to covid-19. it is expected the work can be resumed on 01.06.2021 Executive engineer

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 28/09/2020
Scheduled date of Completion as per agreement 16 Apr 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 07 Sep 2020
Estimate Approval 07 Sep 2020
NIT Approval 07 Sep 2020
Tender Closing 19 Sep 2020
Technichal Pre-Qualification 19 Sep 2020
Price bid opening 22 Sep 2020

Approval Dates

Workorder Date 28 Sep 2020
NA 16 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Parassala WS Sn
Date: 25/07/2022

Work has been completed | 100% Completed

Work had 777/900 completed.And final bill submitted Because of so many householders already self water source like small tube well with pumpset.Secondly so many areas covering KWA pipelines.In these places panchayath roads and sub roads needed for laying 32mm,50mm,63mm size pipes.But these pipes are not included in the schedule.So these places not covering this place for full distributions of houses in this panchayath will achieve the proposed Mavilakadavu Major Project must be completed.This sanctioned work started on 29-05-2021.But the work is not completed with in the specified time.as per the agreement date because of the pipe test connected only on 20-03-2021 due to covid19 restrictions and the labours engaged with this work were effected by covid19 and quarentine during this period.Also there was heavy rainfall durind this period.Various places under the panchayth became containment zone and as per the request of Panchayth president and Hon.MLA,NTA,76Nos of house connections were given at various areas, also there was delay occured from the part of panchayth authorities for giving the list of house holds. Considering the above reasons the work period extended upto 31-01-2022 by hgher authorities.

Parassala WS Sn
Date: 24/07/2022

Work has been completed | 100% Completed

Work had 777/900 completed.And final bill submitted Because of so many householders already self water source like small tube well with pumpset.Secondly so many areas covering KWA pipelines.In these places panchayath roads and sub roads needed for laying 32mm,50mm,63mm size pipes.But these pipes are not included in the schedule.So these places not covering this place for full distributions of houses in this panchayath will achieve the proposed Mavilakadavu Major Project must be completed.This sanctioned work started on 29-05-2021.But the work is not completed with in the specified time.as per the agreement date because of the pipe test connected only on 20-03-2021 due to covid19 restrictions and the labours engaged with this work were effected by covid19 and quarentine during this period.Also there was heavy rainfall durind this period.Various places under the panchayth became containment zone and as per the request of Panchayth president and Hon.MLA,NTA,76Nos of house connections were given at various areas, also there was delay occured from the part of panchayth authorities for giving the list of house holds. Considering the above reasons the work period extended upto 31-01-2022 by hgher authorities.