| Project | JM2020-21 Thiruvananthapuram district Kulathoor GP providing pipe line extension and providing house hold connections in Kulathoor GP (phase 2)J |
|---|---|
| Project Code | TVMJJM08205576P1 |
| Type | Package |
| Main Project | JJM 2020-21 Thiruvananthapuram District Kulathoor Grama Panchayath -Providing pipe line extension and providing household connections in Kulathoor Grama panchayath (Phase 2) |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | JM2020-21 Thiruvananthapuram district Kulathoor GP providing pipe line extension and providing house hold connections in Kulathoor GP (phase 2)J |
| Status | On-going |
| District | Thiruvananthapuram |
| Executing Office | Parassala WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 13900000 |
| TS Number | TS/2020-2021/2020/15397 |
| Technical specification | 1000 water connections can be provided by pipeline extensions after the augmentation of the scheme such as replacing of damaged pipelines and providing for house hold connections by conducting hydraulic feasibility survey for preparing distribution net work map (GIS),making soft drawings for further minor pipeline extensions in densely populated areas facing shortage of drinking water |
| Contractor | DEVARAJ DEVADASAN (Mob: 9446811195) |
| Review Date | Review Message | Review Attended By |
|---|---|---|
| 28 May 2021 | the work is delayed due to covid-19. it is expected the work can be resumed on 01.06.2021 | Executive engineer |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 28/09/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 16 Apr 2021 |
| Expected date of Completion | 31/03/2022 |
| TS Date | 07 Sep 2020 |
|---|---|
| Estimate Approval | 07 Sep 2020 |
| NIT Approval | 07 Sep 2020 |
| Tender Closing | 19 Sep 2020 |
| Technichal Pre-Qualification | 19 Sep 2020 |
| Price bid opening | 22 Sep 2020 |
| Workorder Date | 28 Sep 2020 |
|---|---|
| NA | 16 Oct 2020 |
| Parassala WS Sn |
| Date: 25/07/2022 |
Work has been completed | 100% Completed
Work had 777/900 completed.And final bill submitted Because of so many householders already self water source like small tube well with pumpset.Secondly so many areas covering KWA pipelines.In these places panchayath roads and sub roads needed for laying 32mm,50mm,63mm size pipes.But these pipes are not included in the schedule.So these places not covering this place for full distributions of houses in this panchayath will achieve the proposed Mavilakadavu Major Project must be completed.This sanctioned work started on 29-05-2021.But the work is not completed with in the specified time.as per the agreement date because of the pipe test connected only on 20-03-2021 due to covid19 restrictions and the labours engaged with this work were effected by covid19 and quarentine during this period.Also there was heavy rainfall durind this period.Various places under the panchayth became containment zone and as per the request of Panchayth president and Hon.MLA,NTA,76Nos of house connections were given at various areas, also there was delay occured from the part of panchayth authorities for giving the list of house holds. Considering the above reasons the work period extended upto 31-01-2022 by hgher authorities.
| Parassala WS Sn |
| Date: 24/07/2022 |
Work has been completed | 100% Completed
Work had 777/900 completed.And final bill submitted Because of so many householders already self water source like small tube well with pumpset.Secondly so many areas covering KWA pipelines.In these places panchayath roads and sub roads needed for laying 32mm,50mm,63mm size pipes.But these pipes are not included in the schedule.So these places not covering this place for full distributions of houses in this panchayath will achieve the proposed Mavilakadavu Major Project must be completed.This sanctioned work started on 29-05-2021.But the work is not completed with in the specified time.as per the agreement date because of the pipe test connected only on 20-03-2021 due to covid19 restrictions and the labours engaged with this work were effected by covid19 and quarentine during this period.Also there was heavy rainfall durind this period.Various places under the panchayth became containment zone and as per the request of Panchayth president and Hon.MLA,NTA,76Nos of house connections were given at various areas, also there was delay occured from the part of panchayth authorities for giving the list of house holds. Considering the above reasons the work period extended upto 31-01-2022 by hgher authorities.