- Home
- Amrut 2.0 - Floating Incentive Fund - Pr...
Amrut 2.0 - Floating Incentive Fund - Providing 160 mm PVC Rider main And Alteration of Existing connection Rider main along Mukkilkada - Anandeswram Road
Project |
Amrut 2.0 - Floating Incentive Fund - Providing 160 mm PVC Rider main And Alteration of Existing connection Rider main along Mukkilkada - Anandeswram Road |
Project Code |
TVMAMRUT 2022114170 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Providing 160 mm PVC Rider main And Alteration of Existing connection Rider main along Mukkilkada - Anandeswram Road |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum North PH Dn |
AS Amount (Rs) |
18320000
|
AS Number |
G.O.(Rt)No.473/2023/LSGD |
TS Amount (Rs) |
16697000 |
TS Number |
3358/2023-2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
2000 |
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Amrut 2.0 - Floating Incentive Fund - Providing 160 mm PVC Rider main And Alteration of Existing connection Rider main along Mukkilkada - Anandeswram Road |
Kazhakootam WW Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 May 2024 |
Work On-going |
Thiruvananthapuram PH Dn (N) - EE |
|
14 May 2024 |
Work On-going |
Thiruvananthapuram PH Dn (N) - EE |
|
08 May 2024 |
Total pipe laid 160mm - 2664m, 110mm PVC pipe - 2654m. Full length pressure tested.Gas pipe line work ongoing, so alteration work not started. |
Kazhakootam WW Sn AE |
|
06 May 2024 |
Work on-going |
Kazhakootam WW Sn AE |
|
03 May 2024 |
Work on-going |
Thiruvananthapuram PH Dn (N) - EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/02/2023 |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
23 Feb 2023 |
TS Date |
17 May 2023 |