- Home
- KIIFB- WSS to Mananthavady, Edavaka, Nal...
KIIFB- WSS to Mananthavady, Edavaka, Nalloornadu Villages- KRFB Deposit work Hill Highway- Relaying of distribution pipes from Mananthavady town to 6th mile.
Project |
KIIFB- WSS to Mananthavady, Edavaka, Nalloornadu Villages- KRFB Deposit work Hill Highway- Relaying of distribution pipes from Mananthavady town to 6th mile. |
Project Code |
WYDKIIFB072315884 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
Relaying of distribution pipes from Mananthavady town to 6th mile. |
Status |
On-going |
District |
Wayanad |
Executing Office |
Mananthavady PH Sn |
AS Amount (Rs) |
16000000
|
AS Number |
26/KRFB-PMU/KKD-WYD/KBT/2021 |
TS Amount (Rs) |
15900000 |
TS Number |
TS/12089/2022_26_5_4 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
20 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Nil |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB- WSS to Mananthavady, Edavaka, Nalloornadu Villages- KRFB Deposit work Hill Highway- Relaying of distribution pipes from Mananthavady town to 6th mile. |
Mananthavady PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 May 2024 |
Thonichal to goverment college 110 mm pvc laying in progress |
Mananthavady PH Sn - AE |
|
14 May 2024 |
5500m Pipes laid and First part Bill processed.thonichal inter connection work completed thonichal culvert govt collage pipe laying progress |
Mananthavady PH Sn - AE |
|
02 May 2024 |
Work 50% completed. 5000m Pipes laid and First part Bill processed. |
Sulthan Bathery PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/01/2024 |
Scheduled date of Completion of the Project |
09 Mar 2024 |
Expected date of Completion |
09/03/2024 |
Processing Dates
AS Date |
10 Jul 2023 |
TS Date |
23 Nov 2023 |