PACKAGE I- INTAKE WELL CUM PUMP HOUSE , TRANSFORMER BUILDING etc. PUMPING MAIN

Project PACKAGE I- INTAKE WELL CUM PUMP HOUSE , TRANSFORMER BUILDING etc. PUMPING MAIN
Project Code KNRJJM022213306P1
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Intake well cum pump house 10 m dia , Transformer building, RCC bridge for pipe carrying , DI Pumping main and all electrical works
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 5320
TS Number 10656/2023-2024
Technical specification Intake well cum pump house 10 m dia , Transformer building, RCC bridge for pipe carrying , DI Pumping main and all electrical works

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/08/2023
Scheduled date of Completion as per agreement 22 Feb 2025
Expected date of Completion 31/12/2024

Processing Dates

TS Date 01 Aug 2023
Estimate Approval 01 Aug 2023
NIT Approval 12 Aug 2023
Tender Closing 31 Aug 2023
Technichal Pre-Qualification 12 Aug 2023
Price bid opening 01 Sep 2023

Approval Dates

Workorder Date 23 Sep 2023
NA 13 Oct 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 50% Completed

Construction of intake well completed. Well Steining work up to deck slab completed(30.5 m depth) .Pump house plastering work in progress,90% work completed. Raw water pumping main line supporting bridge completed. Approach bridge RCC completed. Pump house top cover slab RCC completed. electrical room roof slab RCC also completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 50% Completed

Construction of intake well completed. Well Steining work up to deck slab completed(30.5 m depth) .Pump house plastering work in progress,90% work completed. Raw water pumping main line supporting bridge completed. Approach bridge RCC completed. Pump house top cover slab RCC completed. electrical room roof slab RCC also completed.