AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone. (Revised AS -16.67Cr)
Project |
AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone. (Revised AS -16.67Cr) |
Project Code |
TCRGOI0917533 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Components :
1. Laying Distribution network-600mm DI to 160mm PVC-41.179KM
|
Status |
Completed |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
166700000
|
AS Number |
GO(Rt) No. 3170/2017/LSGD |
TS Amount (Rs) |
137200000 |
TS Number |
TS/CE/CR/KWA/48/17-18 |
Total Bill Submitted (Rs) |
114190000 |
Total Bill Paid (Rs) |
114190000 |
Population Benefitted |
34014 |
Capacity in MLD |
7.14 |
Actual Project Completion Date |
31 Mar 2022 |
Coverage |
Pookode Zone of Guruvayur Muncipality-
Population Coverage - 34014 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT -2015-16 Improvements of coverage in Guruvayur Municipality - Laying distribution network for improvement of coverage in Pookode zone. |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Aug 2022 |
Completed |
Nattika Project Dn |
|
03 Aug 2022 |
Completed |
Nattika Project Dn |
|
13 Jun 2022 |
38 km pipe laid & interconnection works completed. Partially commissioned. Balance pipe to be laid in PWD common road (Chavakkad Wadakkanchery Road) with RWPM and CWPM 1950 m completed |
Nattika Project Dn |
|
04 Jun 2022 |
38 km pipe laid & interconnection works completed. Partially commissioned. Balance pipe to be laid in PWD common road (Chavakkad Wadakkanchery Road) with RWPM and CWPM 1950 m completed |
Nattika Project Dn |
|
04 Jun 2022 |
38 km pipe laid & interconnection works completed. Partially commissioned. Balance pipe to be laid in PWD common road (Chavakkad Wadakkanchery Road) with RWPM and CWPM 1950 m completed |
Nattika Proj Dn AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/04/2018 |
Scheduled date of Completion of the Project |
05 Mar 2019 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
28 Sep 2017 |
TS Date |
28 Nov 2017 |