JJM - Eriyad & Edavilangu GP-Common components source improvement of 15MLD water treatment plant- Vythala
Project |
JJM - Eriyad & Edavilangu GP-Common components source improvement of 15MLD water treatment plant- Vythala |
Project Code |
TCRJJM08197027 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - Eriyad & Edavilangu GP-Common components source improvement of 15MLD water treatment plant- supplying, erection & commissioning of 140 HP motor pump set at 15 MLD water treatment plant and Supplying, erection & commissioning of 75 HP vertical turbine motor pump set at rawwater pump house in Vythala |
Status |
Completed |
District |
Thrissur |
Executing Office |
Mala PH Sn |
AS Amount (Rs) |
259320000
|
AS Number |
G.O.(Rt No.541/2020/WRD |
TS Amount (Rs) |
4100000 |
TS Number |
TS/2020-2021/2020/14390 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
35000 |
Capacity in MLD |
15.00 |
Actual Project Completion Date |
05 Feb 2022 |
Coverage |
Methala, Eriyad and Edavilangu Pt |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - Eriyad & Edavilangu GP-Common components source improvement of 15MLD water treatment plant- Vythala |
Mala PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jul 2022 |
Bill submitted to Division office on 10.02.2022 |
Mala PH sn - AE |
|
11 Jul 2022 |
Bill submitted to Division office on 10.02.2022 |
Mala PH sn - AE |
|
29 Jun 2022 |
Bill submitted to Division office on 10.02.2022 |
Mala PH sn - AE |
|
15 Jun 2022 |
Bill submitted to Division office on 10.02.2022 |
Mala PH sn - AE |
|
03 Jun 2022 |
Bill submitted to Division office on 10.02.2022 |
Mala PH sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/09/2020 |
Scheduled date of Completion of the Project |
24 Aug 2021 |
Expected date of Completion |
05/02/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
20 Sep 2020 |