JJM- 2020-21- Manimala Grama Panchayath- Kottayam district-Laying Pipelines and Providing FHTC
Project |
JJM- 2020-21- Manimala Grama Panchayath- Kottayam district-Laying Pipelines and Providing FHTC |
Project Code |
KTMJJM08202835 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
First part -MANIMALA PANCHAYATH Phase -1 zone-1 DMA-I -almost 32 km and providing 1000 FHTCs . Second part- Extensions in already completed NRDWP work-MANIMALA
PANCHAYATH Phase I Zone III by Laying addl. Distribution(10.00 Km) and providing 2750 FHTCs |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
135900000
|
AS Number |
G.O(Rt) No.541/2020/WRD Dated:21-08-2020 135900000.000000 |
TS Amount (Rs) |
86300000 |
TS Number |
TS/2020-2021/2020/2982 Dated: 27-08-2020 |
Total Bill Submitted (Rs) |
31730861 |
Total Bill Paid (Rs) |
31730861 |
Population Benefitted |
12600 |
Capacity in MLD |
9.00 |
Actual Project Completion Date |
31 Oct 2022 |
Coverage |
Manimala panchayath (Part) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Manimala Panchayath - Phase 2 -Package 2 |
Kottayam Project Dn |
|
2 |
JJM- 2020-21- Manimala Grama Panchayath- Kottayam district-Laying Pipelines and Providing FHTC |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Jan 2023 |
36/41km laying completed. PWD permission for Manimala -Pazhayidam - Chenappady road pending(4.1km). |
Kottayam Project Dn AE1 |
|
04 Feb 2022 |
34km/41km laying completed . 1083FHTC/3750 completed and in progress. PWD rejected sanction for Manimala-Pazhayidom-Erumely Road & Karikattur - Mukkada Road. KSTP need to complete their work in Manimala bridge to charge the lines. |
Kottayam Project Dn AE1 |
|
07 Nov 2021 |
25km out of 41 km completed. PWD sanction obtained on 13/10/2021 only except 4.1 km in Paxhayidam-chenappady- erumely road. In other roads works restarted and in progress. 916/3750 connections given. original date of completion expired on 04/05/2021 and the application from contractor for the extension submitted to higher office up to 31/03/2022 considering the ban on sabrimala season up to Jan 15 and the non getting sanction for the Pazhayidam- Chenappady Road . |
Kottayam Project Dn AE1 |
|
01 Oct 2021 |
Meeting conducted at PWD EE's chamber on 30-09-2021 with EE Project Division. AEEs and AEs to discuss the issues related with pending road cutting approvals. |
Kottayam AE 3 |
|
14 Sep 2021 |
22km/41km of pipe laid |
Kottayam Project Dn AE1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/11/2020 |
Scheduled date of Completion of the Project |
04 May 2021 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |