| Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I - APPENDIX-IV- PARIYARAM GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRNABARD1116740P4 |
| Type | Package |
| Main Project | NABARD-RIDF-XXII-WSS TO PATTUVAM AND ADJOINING VILLAGES (JICA AIDED) BALANCE DISTRIBUTION NETWORK - PHASE-I |
| Funding Agency | NABARD |
| Category | NABARD |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-98 (01) |
| Description | In this package, it is proposed to lay balance distribution network of WSS to Pattuvam(JICA) in Pariyaram Panchayath |
| Status | Completed |
| District | Kannur |
| Executing Office | Thaliparambu WS Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 149500000 |
| TS Number | CE/NR/26/2016-17, dated 05.12.2016 of Chief Engineer(NR), Kozhikkode |
| Technical specification | In this package, it is proposed to lay balance distribution network of WSS to Pattuvam(JICA) in Pariyaram Panchayath |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 22/03/2017 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | 06/06/2018 |
| TS Date | 05 Dec 2016 |
|---|---|
| Estimate Approval | 10 Jan 2017 |
| NIT Approval | 10 Jan 2017 |
| Workorder Date | 22 Mar 2017 |
|---|---|
| NA | 01 Apr 2017 |
| Thaliparamba WS Dn EE |
| Date: 31/07/2020 |
Work has been completed | 100% Completed
work has been completed.