Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba -Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21.Panchayath in Malappuram District

Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba -Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21.Panchayath in Malappuram District
Project Code MLPJJM092110135P1
Type Package
Main Project Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Package I - Construction of 8.00 lakhs ltr GLSR , supplying and laying of distribution system to Ward 1,2,18,19,20,21 in Alipparamba Panchayath
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 14040
TS Number 15032/20-21
Technical specification Work started

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/04/2022
Scheduled date of Completion as per agreement 13 Dec 2022
Expected date of Completion 31/05/2023

Processing Dates

TS Date 08 Dec 2021
Estimate Approval 08 Dec 2021
NIT Approval 28 Jan 2022
Tender Closing 09 Feb 2022
Technichal Pre-Qualification 14 Feb 2022
Price bid opening 26 Feb 2022

Approval Dates

Workorder Date 14 Mar 2022
NA 25 Mar 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn EE
Date: 27/06/2025

Work in progress | 95% Completed

2100 nos HTC completed, MS work on culvert completed , 8LL GLSR Completed , pipe line -62 km completed, some interconnection works and GI gap works are pending..

Malappuram Project Dn
Date: 13/06/2025

Work in progress | 95% Completed

2100 nos HTC completed, MS work on culvert completed , 8LL GLSR Completed , pipe line -62 km completed, some interconnection works and GI gap works are pending..