Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba -Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21.Panchayath in Malappuram District
Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba -Package I - Construction of GLSR and Distribution system to ward 1,2,18,19,20,21.Panchayath in Malappuram District |
Project Code |
MLPJJM092110135P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission- 21-22- CWSS to Thazhekkode and Alipparamba Panchayath in Malappuram District
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Package I - Construction of 8.00 lakhs ltr GLSR , supplying and laying of distribution system to Ward 1,2,18,19,20,21 in Alipparamba Panchayath |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
14040 |
TS Number |
15032/20-21 |
Technical specification |
Work started |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
01/04/2022 |
Scheduled date of Completion as per agreement |
13 Dec 2022 |
Expected date of Completion |
31/05/2023 |
Processing Dates
TS Date |
08 Dec 2021 |
Estimate Approval |
08 Dec 2021 |
NIT Approval |
28 Jan 2022 |
Tender Closing |
09 Feb 2022 |
Technichal Pre-Qualification |
14 Feb 2022 |
Price bid opening |
26 Feb 2022 |
Approval Dates
Workorder Date |
14 Mar 2022 |
NA |
25 Mar 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Malappuram Project Dn EE |
Date: 27/06/2025 |
Work in progress | 95% Completed
2100 nos HTC completed, MS work on culvert completed , 8LL GLSR Completed , pipe line -62 km completed, some interconnection works and GI gap works are pending..
Malappuram Project Dn |
Date: 13/06/2025 |
Work in progress | 95% Completed
2100 nos HTC completed, MS work on culvert completed , 8LL GLSR Completed , pipe line -62 km completed, some interconnection works and GI gap works are pending..