State Plan 2023-24-UWSS to Kothamangalam - Supplying, erection and commissioning of one 100 HP CF pumpset and allied works in the CWPH Kothamangalam WTP No. 1

Project State Plan 2023-24-UWSS to Kothamangalam - Supplying, erection and commissioning of one 100 HP CF pumpset and allied works in the CWPH Kothamangalam WTP No. 1
Project Code EKMGOK052314468P1
Type Package
Main Project State Plan 2023-24-UWSS to Kothamangalam - Supplying, erection and commissioning of one 100 HP CF pumpset and allied works in the CWPH Kothamangalam WTP No. 1
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2023-24-UWSS to Kothamangalam - Supplying, erection and commissioning of one 100 HP CF pumpset and allied works in the CWPH Kothamangalam WTP No. 1
Status On-going
District Ernakulam
Executing Office Kothamangalam Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 3770000
TS Number TS/5398/2023_5_3_2 dated 08/11/2023 Reg No.18574/2023-2024
Technical specification Supplying, erection and commissioning of one 100 HP CF pumpset and allied works in the CWPH Kothamangalam WTP No. 1

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/05/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 08 Nov 2023
Estimate Approval 08 Nov 2023
NIT Approval 08 Nov 2023
Tender Closing 20 Nov 2023
Technichal Pre-Qualification 20 Nov 2023
Price bid opening 22 Nov 2023

Approval Dates

Workorder Date 08 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kothamangalam PH Sn 1 - AE
Date: 20/04/2024

Work in progress | 0% Completed

under inspection.

Muvattupuzha PH Dn EE
Date: 08/04/2024

Work has started | 0% Completed

Agreement executed.