Project | JJM (2021-22) - Innovation/ GSM based real time monitoring system under JJM support activities- Supply and erection of Mobile operated GSM module with fully automatic star delta starter for automation ofChelakkulam, Vempilly & Thattamugal pump houses under PH Section Kunnathunadu |
---|---|
Project Code | EKMJJM09218367P1 |
Type | Package |
Main Project | JJM (2021-22) - Innovation/ GSM based real time monitoring system under JJM support activities- Automation of various pump houses under PH Division, Aluva |
Funding Agency | JJM |
Category | JJM - Automation |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM (2021-22) - Innovation/ GSM based real time monitoring system under JJM support activities- Supply and erection of Mobile operated GSM module with fully automatic star delta starter for automation ofChelakkulam, Vempilly & Thattamugal pump houses under PH Section Kunnathunadu |
Status | On-going |
District | Ernakulam |
Executing Office | Pattimattom PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 287900 |
TS Number | TS/2021-2022/2021/39192 Dated: 23-11-2021 |
Technical specification | GSM based real time monitoring system |
Contractor | Wayanad diary Pvt Ltd (Mob: 9544444111) |
Review Date | Review Message | Review Attended By |
---|---|---|
22 Dec 2021 | work is delayed due to the procurement of starter, Panelboard and accessories, dozing pump etc from the manufacturer | A E |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/12/2021 |
---|---|
Scheduled date of Completion as per agreement | 28 Dec 2021 |
Expected date of Completion | 15/02/2022 |
TS Date | 23 Nov 2021 |
---|---|
Estimate Approval | 23 Nov 2021 |
NIT Approval | 22 Dec 2021 |
Tender Closing | 21 Dec 2021 |
Technichal Pre-Qualification | 21 Dec 2021 |
Price bid opening | 22 Dec 2021 |
Workorder Date | 23 Dec 2021 |
---|---|
NA | 30 Dec 2021 |
Pattimattom - Kunnathunadu AE |
Date: 27/02/2022 |
Work has been completed | 100% Completed
Work Completed.
Pattimattom - Kunnathunadu AE |
Date: 25/02/2022 |
Work in progress | 99% Completed
Replacement of damaged NRV in progress.