Plan 2018-19- RWSS to Purthekai - Replacing old and damaged 80mm, 32mm GI pipes using 90mm PVC 10kg/cm2 at Purathekai
Project |
Plan 2018-19- RWSS to Purthekai - Replacing old and damaged 80mm, 32mm GI pipes using 90mm PVC 10kg/cm2 at Purathekai |
Project Code |
KGDGOK08186396 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Replacing old and damaged 80mm, 32mm GI pipes using 90mm PVC 10kg/cm2 at Purathekai (2150m) |
Status |
Completed |
District |
Kasaragod |
Executing Office |
Cheruvathoor Sn |
AS Amount (Rs) |
2500000
|
AS Number |
GO(Rt) No 615/18/WRD |
TS Amount (Rs) |
2500000 |
TS Number |
TS/2018-2019/2018/4488 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
3000 |
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Plan 2018-19- RWSS to Purthekai - Replacing old and damaged 80mm, 32mm GI pipes using 90mm PVC 10kg/cm2 at Puratheka- Package |
Cheruvathoor Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Aug 2022 |
work completed |
Cheruvathur AE |
|
08 Aug 2022 |
work completed |
Cheruvathur AE |
|
04 Aug 2022 |
completed |
Cheruvathur AE |
|
03 Aug 2022 |
work has been completed. |
Cheruvathur AE |
|
25 Jul 2022 |
work has been completed. |
Cheruvathur AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2019 |
Scheduled date of Completion of the Project |
21 May 2019 |
Expected date of Completion |
30/06/2022 |
Processing Dates
AS Date |
20 Aug 2018 |
TS Date |
12 Nov 2018 |