Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II- Part III- Laying Distribution and providing FHTCs in Kodiyamma, Kundappu Kanchikkatta, Mali, Jodgoli, Arikady Pallam area

Project Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II- Part III- Laying Distribution and providing FHTCs in Kodiyamma, Kundappu Kanchikkatta, Mali, Jodgoli, Arikady Pallam area
Project Code KGDJJM08202927P3
Type Package
Main Project Jal Jeevan Mission- Kasaragod District- Kumbala Panchayath- RWSS to Kumbala Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Laying Distribution and providing FHTCs in Kodiyamma, Kundappu Kanchikkatta, Mali, Jodgoli, Arikady Pallam area
Status On-going
District Kasaragod
Executing Office Kumbala PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 25000000
TS Number 15568/2021-2022
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 05 May 2022
Expected date of Completion 30/09/2022

Processing Dates

TS Date 17 Dec 2021
Estimate Approval 17 Dec 2021
Tender Closing 03 Jan 2022
Price bid opening 05 Jan 2022

Approval Dates

Workorder Date 06 Jan 2022
NA 22 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kumbala PH Sn AE
Date: 01/10/2022

Work has been completed | 100% Completed

Work completed on 30/09/2022.

Kumbala PH Sn AE
Date: 24/09/2022

Work in progress | 74% Completed

Work in progress.