- Home
- State plan -Construction of 27 LL OHSR,C...
State plan -Construction of 27 LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l
Project |
State plan -Construction of 27 LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l |
Project Code |
PKDGOK072113918 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
The proposed project is for providing Comprehensive Water Supply Scheme to the entire population of Cherpulassery Municipality at the rate 150 lpcd for the projected population of 45413 forthe year 2050 . The scheme CWSS to Cherpulassery and Adj. Panchayaths is a comprehensive water supply scheme to Cherpulassery Municipality, Anangandi, Thrikkediri and Chalavara Panchayaths. The project is proposed to be executed in 3 phases. Phase – I shall comprise of the common components along with the OHSRs, GLSRs, Clear Water pumps, Clear Water Pumping / Gravity mains, distribution network of the three panchayaths. Phase – II & III shall comprise of the components required for providing water supply to Cherpulassery Municipality and providing FHTCs. |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
100000000
|
AS Number |
G.O.(Rt)No.350/2021/WRD |
TS Amount (Rs) |
100000000 |
TS Number |
TS/2022-23/2022/26147 |
Total Bill Submitted (Rs) |
70266430 |
Total Bill Paid (Rs) |
14306361 |
Population Benefitted |
45413 |
Capacity in MLD |
22.00 |
Actual Project Completion Date |
31 Dec 2024 |
Coverage |
Cherppulassery muncipality & adjoining panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State plan -Construction of 27LL OHSR,CW pump supply & erection, distribution network for Cherpulassery muncipality phase-l |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
27 LL OHSR Cheruppulassery:- Cover slab Completed, Plastering works under progress. Row water pipe lengths-350 mm DI 495 m/500m completed, 400 mm DI 1160 /1170 m completed, 450 mm DI 445/445m completed. 600 mm DI 460/462 m completed, 160 mm PE 3525/3525m completed. |
Palakkad Proj Dn AE 4 |
|
06 May 2024 |
27 LL OHSR Cheruppulassery:- Cover slab Completed, Plastering works under progress. Row water pipe lengths-350 mm DI 495 m/500m completed, 400 mm DI 1160 /1170 m completed, 450 mm DI 445/445m completed. 600 mm DI 460/462 m completed, 160 mm PE 3525/3525m completed. |
Palakkad Proj Dn AE 4 |
|
03 May 2024 |
27 LL OHSR Cheruppulassery:- Cover slab Completed, Plastering works under progress. Row water pipe lengths-350 mm DI 495 m/500m completed, 400 mm DI 1160 /1170 m completed, 450 mm DI 445/445m completed. 600 mm DI 460/462 m completed, 160 mm PE 3525/3525m completed. |
Palakkad Proj Dn AE 4 |
|
01 May 2024 |
27 LL OHSR Cheruppulassery:- Cover slab Completed, Plastering works under progress.Row water pipe lengths-350 mm DI 495 m/500m completed, 400 mm DI 1160 /1170 m completed, 450 mm DI 445/445m completed. 600 mm DI 460/462 m completed, 160 mm PE 3525/3525m completed. |
Palakkad Proj Dn AE 4 |
|
30 Apr 2024 |
27 LL OHSR Cheruppulassery:- Cover slab Completed, Plastering works under progress.Row water pipe lengths-350 mm DI 495 m/500m completed, 400 mm DI 1160 /1170 m completed, 450 mm DI 445/445m completed. 600 mm DI 460/462 m completed, 160 mm PE 3525/3525m completed. |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/10/2022 |
Scheduled date of Completion of the Project |
12 Apr 2023 |
Expected date of Completion |
12/04/2024 |
Processing Dates
AS Date |
08 Jul 2021 |
TS Date |
30 Jun 2022 |