Deposit Work - Pipe line extension work in Ward No. 9 & 19 in VataKara Municipality

Project Deposit Work - Pipe line extension work in Ward No. 9 & 19 in VataKara Municipality
Project Code CLTDEPO12219430
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Laying GI and PVC Pipes
Status On-going
District Kozhikkode
Executing Office Vadakara WSP Sub Dn
AS Amount (Rs) 200000
AS Number E-19331/21
TS Amount (Rs) 200000
TS Number 18648/2021-2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 40
Capacity in MLD 0.03
Actual Project Completion Date 31 May 2022
Coverage Ward 9 & 19 Part
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit Work - Pipe line extension work in Ward No. 9 & 19 in Vatakara Municipality Vadakara WSP Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Nov 2023 ward 9 to be executed Vatakara PH Sn - AE
31 Oct 2023 ward 9 to be executed Vatakara PH Sn - AE
25 Oct 2023 ward 9 to be executed Vatakara PH Sn - AE
03 Jul 2023 partially completed the contractor couldnot continue the work due to hike in cost of GI pipes Vatakara PH Sn - AE
20 Jun 2023 partially completed the contractor couldnot continue the work due to hike in cost of GI pipes Vatakara PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/03/2022
Scheduled date of Completion of the Project 20 May 2022
Expected date of Completion 31/03/2024

Processing Dates

AS Date 02 Dec 2021
TS Date 24 Jan 2022