Project | Deposit Work - Pipe line extension work in Ward No. 9 & 19 in VataKara Municipality |
---|---|
Project Code | CLTDEPO12219430 |
Type | Main project |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Laying GI and PVC Pipes |
Status | On-going |
District | Kozhikkode |
Executing Office | Vadakara WSP Sub Dn |
AS Amount (Rs) | 200000 |
AS Number | E-19331/21 |
TS Amount (Rs) | 200000 |
TS Number | 18648/2021-2022 |
Total Bill Submitted (Rs) | |
Total Bill Paid (Rs) | |
Population Benefitted | 40 |
Capacity in MLD | 0.03 |
Actual Project Completion Date | 31 May 2022 |
Coverage | Ward 9 & 19 Part |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Nov 2023 | ward 9 to be executed | Vatakara PH Sn - AE | |
31 Oct 2023 | ward 9 to be executed | Vatakara PH Sn - AE | |
25 Oct 2023 | ward 9 to be executed | Vatakara PH Sn - AE | |
03 Jul 2023 | partially completed the contractor couldnot continue the work due to hike in cost of GI pipes | Vatakara PH Sn - AE | |
20 Jun 2023 | partially completed the contractor couldnot continue the work due to hike in cost of GI pipes | Vatakara PH Sn - AE |
Date of start of Project | 21/03/2022 |
---|---|
Scheduled date of Completion of the Project | 20 May 2022 |
Expected date of Completion | 31/03/2024 |
AS Date | 02 Dec 2021 |
---|---|
TS Date | 24 Jan 2022 |
Project Officers | View |
---|