69- Renovation of existing civil structures owned by KWA - 2017-18 Calicut Water Supply scheme- Maintenance of Staff Quarters (6Nos) near P.H. Circle, Malaparamba, Kozhikode.
Project |
69- Renovation of existing civil structures owned by KWA - 2017-18 Calicut Water Supply scheme- Maintenance of Staff Quarters (6Nos) near P.H. Circle, Malaparamba, Kozhikode. |
Project Code |
CLTGOK07172649 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Renovation of staff quarters (6 Nos) |
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Kozhikode PH Dn |
AS Amount (Rs) |
2800000
|
AS Number |
G.O.(Rt)NO.606/2017/WRD Dated 17.07.2017 |
TS Amount (Rs) |
2800000 |
TS Number |
SE/PHC/KKD/21/2017-18 Dated 25.01.2018 |
Total Bill Submitted (Rs) |
3138579 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
30 Oct 2019 |
Coverage |
Work completed on 30.10.2019. and final bill submited. Time extension sanctioned and the delay in the work was due to one of the inhabitant has not vacated the quaters in time. The total bill amount including tender excess exceeds the AS. amount. Hence RE submitted for obtaining Revised AS.; |
Packages
No. |
Project Name |
Location |
View |
1 |
69- Renovation of existing civil structures owned by KWA - 2017-18 Calicut Water Supply scheme- Maintenance of Staff Quarters (6Nos) near P.H. Circle, Malaparamba, Kozhikode. |
Kozhikode Aug Med Col Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Mar 2021 |
Work completed on 30.10.2019. and final bill submited. Time extension sanctioned and the delay in the work was due to one of the inhabitant has not vacated the quaters in time. The total bill amount including tender excess exceeds the AS. amount. Hence RE is under preparation for obtaining Revised AS |
Kozhikode PH Dn EE |
|
01 Feb 2021 |
RE submitted |
Kozhikode PH Dn EE |
|
19 Aug 2020 |
Work completed on 30.10.2019. and final bill submited. Time extension sanctioned and the delay in the work was due to one of the inhabitant has not vacated the quaters in time. The total bill amount including tender excess exceeds the AS. amount. Hence RE is under preparation for obtaining Revised AS. |
Kozhikode PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/06/2018 |
Scheduled date of Completion of the Project |
07 Dec 2018 |
Expected date of Completion |
30/10/2019 |
Processing Dates
AS Date |
17 Jul 2017 |
TS Date |
25 Jan 2018 |