DW-Kochi Corporation - Improving water supply to Thampurattiparambu road by replacing old damaged 100 mm AC pipe with 110 mm PVC pipe (6 kg/cm2) for a length of 150 m in old Div no :34 ,38 (new)of Kochi Corporation.
Project |
DW-Kochi Corporation - Improving water supply to Thampurattiparambu road by replacing old damaged 100 mm AC pipe with 110 mm PVC pipe (6 kg/cm2) for a length of 150 m in old Div no :34 ,38 (new)of Kochi Corporation. |
Project Code |
EKMDEPO11208835 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DW-Kochi Corporation - Improving water supply to Thampurattiparambu road by replacing old damaged 100 mm AC pipe with 110 mm PVC pipe (6 kg/cm2) for a length of 150 m in old Div no :34 ,38 (new)of Kochi Corporation. |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kaloor Sub Dn 2 |
AS Amount (Rs) |
200000
|
AS Number |
On line transaction |
TS Amount (Rs) |
200000 |
TS Number |
TS/2020-2021/2020/19393 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
20379 |
Capacity in MLD |
0.25 |
Actual Project Completion Date |
26 Jan 2022 |
Coverage |
DW-Kochi Corporation - Improving water supply to Thampurattiparambu road by replacing old damaged 100 mm AC pipe with 110 mm PVC pipe (6 kg/cm2) for a length of 150 m in old Div no :34 ,38 (new)of Kochi Corporation. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DW-Kochi Corporation - Improving water supply to Thampurattiparambu road by replacing old damaged 100 mm AC pipe with 110 mm PVC pipe (6 kg/cm2) for a length of 150 m in old Div no :34 ,38 (new)of Kochi Corporation. |
Kaloor WW Sn1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 May 2024 |
Bill paid to contractor |
Kaloor AE 1 |
|
02 May 2024 |
Bill paid to contractor |
Kaloor AE 1 |
|
23 Apr 2024 |
Bill paid to contractor |
Kaloor AE 1 |
|
17 Apr 2024 |
Bill paid to contractor |
Kaloor AE 1 |
|
09 Apr 2024 |
Bill paid to contractor |
Kaloor AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/01/2022 |
Scheduled date of Completion of the Project |
26 Jan 2022 |
Expected date of Completion |
21/02/2022 |
Processing Dates
AS Date |
19 Nov 2020 |
TS Date |
28 Dec 2020 |