- Home
- Deposit Work- District panchayath- Water...
Deposit Work- District panchayath- Water supply scheme to Karinkutty HS/ VHSE in Kottathara Grama Panchayath
| Project |
Deposit Work- District panchayath- Water supply scheme to Karinkutty HS/ VHSE in Kottathara Grama Panchayath |
| Project Code |
WYDDEPO032212228 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposit Work- District panchayath- Water supply scheme to Karinkutty HS/ VHSE in Kottathara Grama Panchayath |
| Status |
Completed |
| District |
Wayanad |
| Executing Office |
Kalpetta PH Sn 2 |
| AS Amount (Rs) |
1100000
|
| AS Number |
DP-14-289/22 |
| TS Amount (Rs) |
1100000 |
| TS Number |
TS/2022-2023/2022/1736 |
| Total Bill Submitted (Rs) |
758407 |
| Total Bill Paid (Rs) |
758407 |
| Population Benefitted |
500 |
| Capacity in MLD |
1.00 |
| Actual Project Completion Date |
23 Dec 2022 |
| Coverage |
Kottathara GP |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Deposit Work- District panchayath- Water supply scheme to Karinkutty HS/ VHSE in Kottathara Grama Panchayath |
Kalpetta PH Sn 2 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 14 Oct 2024 |
Bill paid&UC Issued |
Sulthan Bathery PH Dn EE |
|
| 12 Jul 2023 |
Work completed and Bill submitted. |
Sulthan Bathery PH Dn EE |
|
| 01 Jul 2023 |
Bill Scrutinizing under sub Division |
Kalpetta PH Sn 2 - AE |
|
| 27 Jun 2023 |
Bill Scrutinizing under sub Division |
Kalpetta PH Sn 2 - AE |
|
| 24 Jun 2023 |
Bill Scrutinizing under sub Division |
Kalpetta PH Sn 2 - AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
27/07/2022 |
| Scheduled date of Completion of the Project |
27 Jan 2023 |
| Expected date of Completion |
27/01/2023 |
Processing Dates
| AS Date |
21 Mar 2022 |
| TS Date |
20 Jun 2022 |