Project | State Plan 2018-19 - TSS - Supply of new pump sets at Mudavanmughal |
---|---|
Project Code | TVMGOK02191807 |
Type | Main project |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Supply of new pump sets at Mudavanmughal G.O.(Rt.) No. 84/2019/WRD dated 06.02.2019 |
Status | Completed |
District | Thiruvananthapuram |
Executing Office | Kuriathy Sewerage Sn 3 |
AS Amount (Rs) | 1300000 |
AS Number | 84/2019/WRD |
TS Amount (Rs) | 1208000 |
TS Number | 247/2019-2020 |
Total Bill Submitted (Rs) | 0 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 10000 |
Capacity in MLD | 3.00 |
Actual Project Completion Date | 13 Oct 2021 |
Coverage | Pump installation work |
Implementation Schedule | Download |
Work Plan | Download |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Oct 2021 | 100% : Work completed. | Kuriathy Sew Sub Dn AEE | |
13 Oct 2021 | 100% : Work completed. | Kuriyathy Sew Sn 3 AE | |
08 Oct 2021 | 98% : Trial run in progress | Kuriyathy Sew Sn 3 AE | |
30 Sep 2021 | trial run in progress | Kuriathy Sew Sub Dn AEE | |
28 Sep 2021 | 95% : 2 nos. of 30 HP submersible pumpset installation completed, pumping line laid. Panel board installation in progress. | Kuriyathy Sew Sn 3 AE |
Date of start of Project | 26/08/2020 |
---|---|
Scheduled date of Completion of the Project | 25 Feb 2021 |
Expected date of Completion | 15/10/2021 |
AS Date | 06 Feb 2019 |
---|---|
TS Date | 03 May 2019 |
Project Officers | View |
---|