JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
Project Code
KTMJJM08219884
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
Status
Completed
District
Kottayam
Executing Office
Kaduthuruthy PH Sub Dn
AS Amount (Rs)
45097000
AS Number
45097000
TS Amount (Rs)
16590000
TS Number
TS/2021-2022/2021/29595
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
45.00
Actual Project Completion Date
26 Oct 2022
Coverage
Packages
No.
Project Name
Location
View
1
JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
Kaduthuruthy Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
26 Oct 2022
63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300
Kaduthuruthy Dn EE
25 Oct 2022
63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300
Kaduthuruthy Dn EE
24 Oct 2022
63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300
Kaduthuruthy Dn EE
23 Oct 2022
63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300
Kaduthuruthy Dn EE
22 Oct 2022
63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300