Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.

Project JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
Project Code KTMJJM08219884
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath.
Status Completed
District Kottayam
Executing Office Kaduthuruthy PH Sub Dn
AS Amount (Rs) 45097000
AS Number 45097000
TS Amount (Rs) 16590000
TS Number TS/2021-2022/2021/29595
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD 45.00
Actual Project Completion Date 26 Oct 2022
Coverage

Packages

No. Project Name Location View
1 JJM 2020-21 Chempu Panchayath. PHASE I Balance Works. Retrofitting/Augmenting/Extending existing distribution system and providing FHTCs in various wards of Chempu Grama Panchayath. Kaduthuruthy Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2022 63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300 Kaduthuruthy Dn EE
25 Oct 2022 63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300 Kaduthuruthy Dn EE
24 Oct 2022 63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300 Kaduthuruthy Dn EE
23 Oct 2022 63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300 Kaduthuruthy Dn EE
22 Oct 2022 63mm PVC laying -6500mtr, 90 mm PVC laying - 996m and 63mm HDPE laying -3000mtr, Providing FHTCs -300 Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/03/2022
Scheduled date of Completion of the Project 20 Jun 2022
Expected date of Completion 31/07/2022

Processing Dates

AS Date 21 Aug 2021
TS Date 25 Feb 2022

Other details

Project Officers View