STATE PLAN 2021-Optimisation of production and transmission.Renovation of WTP-Modernisation of 72MLD Water Treatment plant and pumping station Building premises.

Project STATE PLAN 2021-Optimisation of production and transmission.Renovation of WTP-Modernisation of 72MLD Water Treatment plant and pumping station Building premises.
Project Code TVMGOK06217747
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description STATE PLAN 2021-Optimisation of production and transmission-Renovation of WTP-Modernisation of 72MLD Water Treatment plant and pumping station Building premises
Status Completed
District Thiruvananthapuram
Executing Office Aruvikkara WS Gen Sn
AS Amount (Rs) 9100000
AS Number KWA/JB/PIU-1/AE4/State Plan/OPT/05/21-22
TS Amount (Rs) 8946000
TS Number 12779/2021-2022
Total Bill Submitted (Rs) 10718600
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 72.00
Actual Project Completion Date 04 Nov 2022
Coverage STATE PLAN 2021-Optimisation of production and transmission.Renovation of WTP-Modernisation of 72MLD Water Treatment plant and pumping station Building premises.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 STATE PLAN 2021-Optimisation of production and transmission.Renovation of WTP-Modernisation of 72MLD Water Treatment plant and pumping station Building premises. Aruvikkara Sn 5

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Nov 2022 work completed satisfactorily Aruvikkara HW Dn EE
04 Nov 2022 work completed satisfactorily Aruvikkara HW Gen Sn AE
04 Nov 2022 work completed satisfactorily Aruvikkara HW Gen Sn AE
07 Nov 2022 Final cleaning works around the plant premises Aruvikkara HW Dn EE
02 Nov 2022 Final cleaning works around the plant premises Aruvikkara HW Gen Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/02/2022
Scheduled date of Completion of the Project 01 Jun 2022
Expected date of Completion 01/06/2022

Processing Dates

AS Date 16 Jun 2021
TS Date 10 Nov 2021

Other details

Project Officers View