Cherthala Municipality - Extn of pipe line in ward nos 1,21,22,23,25,& 26
Project |
Cherthala Municipality - Extn of pipe line in ward nos 1,21,22,23,25,& 26 |
Project Code |
ALPDEPO10219607 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work - Annual project 2020-21- project no 71/2021 |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Cherthala PH Sub Dn |
AS Amount (Rs) |
2710000
|
AS Number |
PW1-1666/20 of 2021-22 |
TS Amount (Rs) |
2710000 |
TS Number |
TS/2021-2022/2021/5120 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1200 |
Capacity in MLD |
102.00 |
Actual Project Completion Date |
28 Nov 2022 |
Coverage |
Cherthala Municipality wards 1,21,22,23,25,& 26 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Extn of pipe line in various wards of cherthala Municipality |
Cherthala PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Nov 2022 |
2894 m/2894 m pipe laid and work completed. |
Cherthala PH Section - AE |
|
23 Nov 2022 |
2794 m/2894 pipe laid |
Cherthala PH Section - AE |
|
14 Nov 2022 |
2700 m/2894 pipe laid |
Cherthala PH Section - AE |
|
09 Nov 2022 |
2400 m pipe laid. |
Cherthala PH Section - AE |
|
17 Oct 2022 |
2000 m pipe laid. |
Cherthala PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/04/2022 |
Scheduled date of Completion of the Project |
21 May 2022 |
Expected date of Completion |
30/11/2022 |
Processing Dates
AS Date |
04 Oct 2021 |
TS Date |
02 Feb 2022 |