JJM 2020-21- Chirakadavu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC

Project JJM 2020-21- Chirakadavu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC
Project Code KTMJJM08184285
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying new distribution of 27.km from OHSR at Karuthamanjadi in Cheruvally Village from CWSS to Manimala , Extension of 11.2km of pipelines in existing distribution from ARWSS to Kanjirapally, Elikulam & Chorakadav panchayaths and providing 2100 FHTCs in total Chirakadav panchayath
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 153900000
AS Number GO (Rt)No541/2020/WRD
TS Amount (Rs) 89400000
TS Number TS/2020-2021/2020/19293
Total Bill Submitted (Rs) 47607334
Total Bill Paid (Rs) 47607334
Population Benefitted 10500
Capacity in MLD 9.00
Actual Project Completion Date 31 Dec 2021
Coverage Part of Chirakadav Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2020-21- Chirakadavu Grama Panchayat- Kottayam District- Laying Pipelines and providing FHTC Kottayam Project Dn
2 JJM- 2020-21 - CHIRAKKADAVU PANCHAYATH- KOTTAYAM DISTRICT - Phase IPACKAGE 2 - LAYING PIPE LINES AND PROVIDING FHTCs (in Phase 3 DMA II), Construction of Compound Wall for OHSR at Karuthamanjadi Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Jan 2023 Package 1 laying almost completed except 1.7km in NH 183 in which permission pending from MoRTH. Package 2 work ongoing 4.5km laying permission through Mooleplav- Powath Kavala road to be obtained from PWD. PWD denied as there is a vigilance enquiry going on the same road against their work. Kottayam Project Dn AE1
04 Feb 2022 30km /38.6km laid. 1.7 KM to be laid through NH 183 (KK road) application pending with MoRTH. 735FHTC/2100 completed . Protest by the panchayath against doing work without RR of panchayath roads delaying the work as the provision for RR was less in the work Kottayam Project Dn AE1
28 Nov 2021 Sanction was accorded in the District Infrastructure Meeting (DIC) held on 22.11.2021 to lay pipes for 2.6 km along Kanjirapally- Manimala Road which was handed over to KRFB by PWD . Accordingly pipe laying works started on 27.11.2021. Kottayam Project Dn EE
07 Nov 2021 24.5 km out of 38.6km laid . 1.7 KM to be laid through NH 183 (KK road) application pending with MoRTH. 2.6km sanction to be obtained from PWD for laying through Kanjirapally- Manimala Road which is handed over to KRFB for work. 4km line included in this work is included in the KSTP road work and the same to be laid wherever necessary as rider lines once the KSTP work completed. Other road works in progress .650 out of 2100 FHTC completed. Work is getting delayed due to the protest by the panchayath & public while cutting to be made through newly concreted /tarred roads and the provision for restoration was less in the work. Original date of completion was 05/05/2021 and the Application from contractor is submitted to higher officefor extension up to 30-11-2021. Kottayam Project Dn AE1
07 Nov 2021 23km out of 38.6km laid . 1.7 KM to be laid through NH 183 (KK road) application pending with MoRTH. 2.6km sanction to be obtained from PWD for laying through Kanjirapally- Manimala Road which is handed over to KRFB for work. 4km line included in this work is included in the KSTP road work and the same to be laid wherever necessary as rider lines once the KSTP work completed. Other road works in progress .650 out of 2100 FHTC completed. Work is getting delayed due to the protest by the panchayath & public while cutting to be made through newly concreted /tarred roads and the provision for restoration was less in the work. Original date of completion was 05/05/2021 and the Application from contractor is submitted to higher officefor extension up to 30-11-2021. Kottayam Project Dn AE1

Project Review

See All Review messages
Review Date Review Message Review Attended By
18 Jun 2021 Add correspondence with PWD and KSTP regarding road issues in the documents. ADD PHOTOGRAPHS U CAN ESTIMATE GI PIPE REQUIREMENTS WITH NEW RATE AND CAN ARRANGE THE WORK USING balance AS EE AEE AE
18 Jun 2021 Add correspondence with PWD and KSTP regarding road issues in the documents. ADD PHOTOGRAPHS U CAN ESTIMATE GI PIPE REQUIREMENTS WITH NEW RATE AND CAN ARRANGE THE WORK USING balance AS EE AEE AE

Duration & Sanction dates

Date of start of Project 20/11/2020
Scheduled date of Completion of the Project 05 May 2021
Expected date of Completion 31/03/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 08 Sep 2020