DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work

Project DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work
Project Code KLMDEPO112213604
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work
Status Completed
District Kollam
Executing Office Chavara PH Sub Dn
AS Amount (Rs) 40000
AS Number PW2-11157/2022
TS Amount (Rs) 40000
TS Number WRD/KWA-CEP/EST-TS/101/20225-7-6
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 500
Capacity in MLD 0.00
Actual Project Completion Date 15 Feb 2024
Coverage Water supply connection to Gas Crematorium
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work Oachira PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Feb 2024 Work completed Oachira AE
13 Feb 2024 Connection process ongoing. Oachira AE
12 Feb 2024 Connection process ongoing. Oachira AE
07 Feb 2024 Connection process ongoing. Oachira AE
04 Feb 2024 Connection process ongoing. Oachira AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/01/2023
Scheduled date of Completion of the Project 07 Feb 2023
Expected date of Completion 15/01/2024

Processing Dates

AS Date 23 Nov 2022
TS Date 20 Jan 2023

Other details

Project Officers View