KIIFB - Augumentation of WSS To Angamaly Constituency -Part -II

Project KIIFB - Augumentation of WSS To Angamaly Constituency -Part -II
Project Code EKMKIIFB1118478
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Part -2. WSS to Malayattoor Neeleeswaram & Ayyampuzha Panchayaths . PART II consists two packages.Package-1) 8 MLD WTP with clear water sump at illithode and Renovation of existing structures-
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
AS Amount (Rs) 425800000
AS Number GO(Rt)184/2018/WRD
TS Amount (Rs) 109400000
TS Number TS/2020-2021/2019/13363
Total Bill Submitted (Rs) 79022350
Total Bill Paid (Rs) 79022350
Population Benefitted 49095
Capacity in MLD 8.00
Actual Project Completion Date 30 Oct 2023
Coverage Malayatoor-Neeleeswaram and Ayyampuzha panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB - Aug of WSS To Angamaly Constituency- PART - II Package I Project Division Perumbavoor
2 KIIFB - Aug of WSS To Angamaly Constituency- PART - II Package II Project Division Perumbavoor

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Apr 2024 part 2 contains 2 packages - package 1 -8 MLD WTP Civil work completed but not commissioned due to pending of Power connection from KSEB package 2 - tender work in progress Perumbavoor Project Dn AE1
10 Apr 2024 part 2 contains 2 packages - package 1 -8 MLD WTP Civil work completed but not commissioned due to pending of Power connection from KSEB package 2 - tender work in progress Perumbavoor Project Dn AE1
03 Apr 2024 part 2 contains 2 packages - package 1 -8 MLD WTP Civil work completed but not commissioned due to pending of Power connection from KSEB package 2 - tender work in progress Perumbavoor Project Dn AE1
27 Mar 2024 part 2 contains 2 packages - package 1 -8 MLD WTP Civil work completed but not commissioned due to pending of Power connection from KSEB package 2 - tender work in progress Perumbavoor Project Dn AE1
20 Mar 2024 part 2 contains 2 packages - package 1 -8 MLD WTP Civil work completed but not commissioned due to pending of Power connection from KSEB package 2 - tender work in progress Perumbavoor Project Dn AE1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/01/2021
Scheduled date of Completion of the Project 12 Oct 2022
Expected date of Completion 30/10/2023

Processing Dates

AS Date 12 Nov 2018
TS Date 25 Sep 2020

Other details

Project Officers View