Project | State Plan 2022-23 - WQMS and Effluent Quality Testing Labs under QC Division Kochi -Setting up of Effluent Testing Laboratory at Vypin in Ernakulam District- |
---|---|
Project Code | EKMGOK052212086P1 |
Type | Package |
Main Project | State Plan 2022-23 - WQMS and Effluent Quality Testing Labs under QC Division Kochi-Setting up of Effluent Testing Laboratory at Vypin in Ernakulam District - Civil Works |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | State Plan 2022-23 - WQMS and Effluent Quality Testing Labs under QC Division Kochi -Setting up of Effluent Testing Laboratory at Vypin in Ernakulam District- Civil Works |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva QC Sn Lab |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 862000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/2338/2022_5_1 |
Technical specification | civil work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/08/2022 |
---|---|
Scheduled date of Completion as per agreement | 11 Apr 2023 |
Expected date of Completion | 28/02/2023 |
TS Date | 20 Aug 2022 |
---|---|
Estimate Approval | 20 Aug 2022 |
NIT Approval | 29 Aug 2022 |
Tender Closing | 28 Sep 2022 |
Workorder Date | 12 Dec 2022 |
---|---|
NA | 12 Dec 2022 |
Kochi QC Sub Division - AEE |
Date: 11/05/2023 |
Work has been completed | 100% Completed
Final bill submitted.
Kochi QC Sub Division - AEE |
Date: 05/05/2023 |
Work has been completed | 100% Completed
Work completed and bill prepared.