- Home
- Deposit-Madayi panchayath-Replacing PVC...
Deposit-Madayi panchayath-Replacing PVC pipe to GI pipe(Tsunami colony)
Project |
Deposit-Madayi panchayath-Replacing PVC pipe to GI pipe(Tsunami colony) |
Project Code |
KNRGOK112416913 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
4215-01-800-89 |
Description |
Deposit-Madayi panchayath-Replacing PVC pipe to GI pipe(Tsunami colony) |
Status |
Completed |
District |
Kannur |
Executing Office |
Pilathra WS Sn |
AS Amount (Rs) |
20000
|
AS Number |
401024/DPDC02/GPO/2024/3776/(1) |
TS Amount (Rs) |
20000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/22643/2024_26_2_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit-Madayi panchayath-Replacing PVC pipe to GI pipe(Tsunami colony) |
Pilathra WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Feb 2025 |
work completed |
Pilathara WS Sn - AE |
|
14 Jan 2025 |
work oder issued |
Pilathara WS Sn - AE |
|
06 Jan 2025 |
work oder issued |
Pilathara WS Sn - AE |
|
24 Dec 2024 |
work oder issued |
Pilathara WS Sn - AE |
|
12 Dec 2024 |
TS Approved |
Pilathara WS Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
06 Nov 2024 |
TS Date |
22 Nov 2024 |