- Home
- State Plan 2021-22: Implementation of th...
State Plan 2021-22: Implementation of the scheme- UWSS to Changanasserry - Design and construction of 15 LL capacity OHSR, Office complex and alied works at Perunna
Project |
State Plan 2021-22: Implementation of the scheme- UWSS to Changanasserry - Design and construction of 15 LL capacity OHSR, Office complex and alied works at Perunna |
Project Code |
KTMGOK012214196 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan 2021-22: Implementation of the scheme- UWSS to Changanasserry - Design and construction of 15 LL capacity OHSR, Office complex and alied works at Perunna |
Status |
On-going |
District |
Kottayam |
Executing Office |
Changanassery Sn |
AS Amount (Rs) |
100000000
|
AS Number |
GO(Rt) No.8/2022/WRD |
TS Amount (Rs) |
77900000 |
TS Number |
TS/2022-2023/2022/15277 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
20000 |
Capacity in MLD |
1.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
West side of Changanasserry Municiplaity |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2021-22: Implementation of the scheme- UWSS to Changanasserry - Design and construction of 15 LL capacity OHSR, Office complex and alied works at Perunna |
Changanassery Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Oct 2023 |
Concreting of piles going on. |
Changanaserry PH Sn - AE |
|
25 Sep 2023 |
Concreting of piles going on. |
Changanaserry PH Sn - AE |
|
16 Sep 2023 |
Concreting of piles going on.
|
Changanaserry PH Sn - AE |
|
13 Sep 2023 |
Concreting of piles going on.
|
Changanaserry PH Sn - AE |
|
11 Sep 2023 |
Concreting of piles going on.
|
Changanaserry PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/01/2022 |
Scheduled date of Completion of the Project |
16 Nov 2023 |
Expected date of Completion |
16/11/2023 |
Processing Dates
AS Date |
04 Jan 2022 |
TS Date |
03 May 2022 |