KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work
Project |
KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work |
Project Code |
TCRDEPO082315561 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work |
Status |
On-going |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
12875000
|
AS Number |
AE2/PVC/KRFB-PMU/EKM-TSR/201 |
TS Amount (Rs) |
12800000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/5340/2022_26_1_1 Dated: 21-09-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
Date is not specified |
Coverage |
WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work |
Vadakanchery PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 May 2024 |
Work on going-44%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. |
Vadakkanchery PH Sn |
|
15 May 2024 |
Work on going-44%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. |
Vadakkanchery PH Sn |
|
14 May 2024 |
Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. |
Vadakkanchery PH Sn |
|
13 May 2024 |
Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. |
Vadakkanchery PH Sn |
|
09 May 2024 |
Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/11/2023 |
Scheduled date of Completion of the Project |
03 Jun 2024 |
Expected date of Completion |
03/06/2024 |
Processing Dates
AS Date |
08 Aug 2023 |
TS Date |
21 Sep 2023 |