Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work

Project KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work
Project Code TCRDEPO082315561
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 12875000
AS Number AE2/PVC/KRFB-PMU/EKM-TSR/201
TS Amount (Rs) 12800000
TS Number WRD/KWA-CE(CR)/EST_TS/5340/2022_26_1_1 Dated: 21-09-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 0.10
Actual Project Completion Date Date is not specified
Coverage WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-KIIFB-Budget work 2016-17-Improvements to Peechi Vazhani tourism Corridor-Replacing exsisting pipes lines under WSP section Wadakkanchery - From Karumathra to Kundukad-Pipeline Work Vadakanchery PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 Work on going-44%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. Vadakkanchery PH Sn
15 May 2024 Work on going-44%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. Vadakkanchery PH Sn
14 May 2024 Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. Vadakkanchery PH Sn
13 May 2024 Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. Vadakkanchery PH Sn
09 May 2024 Work on going-42%. Work commenced, and pipe laying completed in the area cleared by KIIFB, but their road alignment changed and the laid pipe lines to be shifted from the existing trenches. Hence the work is temporarily stopped and the future pipe laying is done only after fixing the final alignment of the road .Also communicated with KRFB Project Engineer Mr. Sajith to fix the final alignment. Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/11/2023
Scheduled date of Completion of the Project 03 Jun 2024
Expected date of Completion 03/06/2024

Processing Dates

AS Date 08 Aug 2023
TS Date 21 Sep 2023

Other details

Project Officers View