AMRUT-2.0- Augmentation of UWSS to Mannarkkad Municipality- Providing FHTCs and pipe line extension

Project AMRUT-2.0- Augmentation of UWSS to Mannarkkad Municipality- Providing FHTCs and pipe line extension
Project Code PKDAMRUT2112212863
Type Main project
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description AMRUT-2.0- Augmentation of UWSS to Mannarkkad Municipality- Providing FHTCs and pipe line extension
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 76800000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 66000000
TS Number WRD/KWA-CE(NR)/EST_TS/12723/2023_26_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 25500
Capacity in MLD 0.88
Actual Project Completion Date Date is not specified
Coverage Mannarkkad Municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-2.0- Augmentation of UWSS to Mannarkkad Municipality- Providing FHTCs and pipe line extension Mannarkkad (Agali) Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Soil testing (3 pit)done on 5th & 6th Feb 2024.Structural Design of OSHR tank in progress. Connection details details received on 12th Feb 2024.FHTC works ongoing 56 FHTC are Geo taged . Mannarkkad PH Sn AE
10 May 2024 Soil testing (3 pit)done on 5th & 6th Feb 2024.Structural Design of OSHR tank in progress. Connection details details received on 12th Feb 2024.FHTC works ongoing 56 FHTC are Geo taged . Mannarkkad PH Sn AE
06 May 2024 Soil testing (3 pit)done on 5th & 6th Feb 2024.Structural Design of OSHR tank in progress. Connection details details received on 12th Feb 2024.FHTC works ongoing 56 FHTC are Geo taged . Mannarkkad PH Sn AE
02 May 2024 Soil testing (3 pit)done on 5th & 6th Feb 2024.Structural Design of OSHR tank in progress. Connection details details received on 12th Feb 2024.FHTC works ongoing Mannarkkad PH Sn AE
27 Apr 2024 Soil testing (3 pit)done on 5th & 6th Feb 2024.Structural Design of OSHR tank in progress. Connection details details received on 12th Feb 2024.FHTC works ongoing Mannarkkad PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/11/2023
Scheduled date of Completion of the Project 20 Nov 2024
Expected date of Completion 30/11/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 05 Sep 2023

Other details