- Home
- Jal Jeevan Mission (jjm) RWSS to Wandoor...
Jal Jeevan Mission (jjm) RWSS to Wandoor phase2 and 1-shifting of existing FHTC to new distribution network -pipe line work
Project |
Jal Jeevan Mission (jjm) RWSS to Wandoor phase2 and 1-shifting of existing FHTC to new distribution network -pipe line work |
Project Code |
MLPJJM102316691 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Jal Jeevan Mission (jjm) RWSS to Wandoor phase2 and 1-shifting of existing FHTC to new distribution network -pipe line work |
Status |
On-going |
District |
Malappuram |
Executing Office |
Vandoor PH Sn |
AS Amount (Rs) |
35000000
|
AS Number |
GO.(RT)NO.897/2023/WRD |
TS Amount (Rs) |
30040679 |
TS Number |
WRD/KWA-CE(NR)TR/14246/12023-26-1-1/1 |
Total Bill Submitted (Rs) |
15939751 |
Total Bill Paid (Rs) |
|
Population Benefitted |
7500 |
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (jjm) RWSS to Wandoor phase2 and 1-shifting of existing FHTC to new distribution network -pipe line work |
Vandoor PH Sn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/10/2023 |
Scheduled date of Completion of the Project |
24 Feb 2024 |
Expected date of Completion |
05/03/2025 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
10 Jan 2024 |