Project | JJM - Providing FHTC to Rural house holds in Vazhakkulam Panchayath Phase II, Part 7 |
---|---|
Project Code | EKMJJM08203026P4 |
Type | Package |
Main Project | JJM - Providing FHTC to Rural house holds in Vazhakkulam Panchayath |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2020-21-Vazhakulam Panchayath in Ernakulam District-Phase II-Part VIIExtension of Pipe Line in Ward no. 17 and Providing Functional House Hold Tap Connections(FHTC) |
Status | On-going |
District | Ernakulam |
Executing Office | Aluva JJM Section |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 10000000 |
TS Number | ORDER No. TS/2021-2022/2022/11612 Dated: 28-03-2022 |
Technical specification | TS/2020-2021/2020/13862 Dated: 27-08-2020 Reg .No. 6600/2020-2021 |
Contractor | T A MEETHIYAN (Mob: 9744188714) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 31 Dec 2022 |
Expected date of Completion | 30/06/2023 |
TS Date | 28 Mar 2022 |
---|---|
Estimate Approval | 28 Apr 2022 |
Tender Closing | 05 Apr 2022 |
Price bid opening | 07 Apr 2022 |
Workorder Date | 13 Apr 2022 |
---|
Pattimattom - Kunnathunadu AE |
Date: 18/05/2024 |
Work has been completed | 100% Completed
final bill submitted - 209 FHTC given.
Pattimattom - Kunnathunadu AE |
Date: 17/05/2024 |
Work has been completed | 100% Completed
final bill submitted - 209 FHTC given.