DEPOSIT-Kochi Corporation-Replacing old and damaged 63mm PVC pipe by 90mm PVC pipe (10kg/cm2) at Azhakanthara stadium cross road avenue-5 in Div.No. 65P (old 37) of Kochi Corporation-Pipeline Work
Project |
DEPOSIT-Kochi Corporation-Replacing old and damaged 63mm PVC pipe by 90mm PVC pipe (10kg/cm2) at Azhakanthara stadium cross road avenue-5 in Div.No. 65P (old 37) of Kochi Corporation-Pipeline Work |
Project Code |
EKMDEPO062315088 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Kochi Corporation-Replacing old and damaged 63mm PVC pipe by 90mm PVC pipe (10kg/cm2) at Azhakanthara stadium cross road avenue-5 in Div.No. 65P (old 37) of Kochi Corporation-Pipeline Work |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Vytilla Section 2 |
AS Amount (Rs) |
411000
|
AS Number |
CCPC7/1154/22 |
TS Amount (Rs) |
411000 |
TS Number |
10124/2023-2024 |
Total Bill Submitted (Rs) |
282250 |
Total Bill Paid (Rs) |
282250 |
Population Benefitted |
120 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
31 Dec 2023 |
Coverage |
DEPOSIT-Kochi Corporation-Replacing old and damaged 63mm PVC pipe by 90mm PVC pipe (10kg/cm2) at Azhakanthara stadium cross road avenue-5 in Div.No. 65P (old 37) of Kochi Corporation-Pipeline Work |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Kochi Corporation-Replacing old and damaged 63mm PVC pipe by 90mm PVC pipe (10kg/cm2) at Azhakanthara stadium cross road avenue-5 in Div.No. 65P (old 37) of Kochi Corporation-Pipeline Work |
Vytilla Section 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Feb 2024 |
Final bill submitted |
Vytilla Section AE - 2 |
|
12 Jan 2024 |
Work completed |
Vytilla Section AE - 2 |
|
31 Dec 2023 |
Work completed |
Vytilla Section AE - 2 |
|
30 Dec 2023 |
House connections shifting work going on |
Kochi PH Dn EE |
|
27 Dec 2023 |
House connections shifting work going on |
Vytilla Section AE - 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/10/2023 |
Scheduled date of Completion of the Project |
17 Nov 2023 |
Expected date of Completion |
29/02/2024 |
Processing Dates
AS Date |
14 Jun 2023 |
TS Date |
26 Jul 2023 |