Deposit work – Providing Non Domestic Water Supply Connection to Homoeo hospital, Ayurveda hospital, Krishi Bhavan,Muhamma Grama panchayath office and Pakalveedu in Muhamma Panchayath
Project |
Deposit work – Providing Non Domestic Water Supply Connection to Homoeo hospital, Ayurveda hospital, Krishi Bhavan,Muhamma Grama panchayath office and Pakalveedu in Muhamma Panchayath |
Project Code |
ALPDEPO052211995 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work – Providing Non Domestic Water Supply Connection to Homoeo hospital, Ayurveda hospital, Krishi Bhavan,Muhamma Grama panchayath office and Pakalveedu in Muhamma Panchayath |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Cherthala PH Sub Dn |
AS Amount (Rs) |
76000
|
AS Number |
1000156/2020/17440 |
TS Amount (Rs) |
76000 |
TS Number |
6503/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
10 Nov 2022 |
Coverage |
5 public places in Muhamma panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work – Providing Non Domestic Water Supply Connection to Homoeo hospital, Ayurveda hospital, Krishi Bhavan,Muhamma Grama panchayath office and Pakalveedu in Muhamma Panchayath |
Cherthala PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2023 |
Bill submitted to Division Office |
Cherthala PH SUb Dn |
|
23 Nov 2022 |
Work completed . bill under preparation |
Cherthala PH Section - AE |
|
09 Nov 2022 |
Work completed on 7/11/2022. |
Cherthala PH Section - AE |
|
08 Nov 2022 |
bill in the preparation |
Cherthala PH Section - AE |
|
26 Oct 2022 |
e tapp processing completed. physical work at site started and in progress. |
Cherthala PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/07/2022 |
Scheduled date of Completion of the Project |
07 Sep 2022 |
Expected date of Completion |
30/11/2022 |
Processing Dates
AS Date |
28 May 2022 |
TS Date |
09 Jun 2022 |