KIIFB-2017/18-Improvements to Hill Highway Kolichal Cherupuzha road-KM0/000 to 30/377BM&BC in Kasaragod District-Shifting of utilities of WSS to Malom

Project KIIFB-2017/18-Improvements to Hill Highway Kolichal Cherupuzha road-KM0/000 to 30/377BM&BC in Kasaragod District-Shifting of utilities of WSS to Malom
Project Code KGDKIIFB092212433
Type Main project
Funding Agency KIIFB
Category PWD Deposit
Type of scheme Water Supply
Scheme KIIFB
Description KIIFB-2017/18-Improvements to Hill Highway Kolichal Cherupuzha road-KM0/000 to 30/377BM&BC in Kasaragod District-Shifting of utilities of WSS to Malom
Status Completed
District Kasaragod
Executing Office Kanhangad PH Sub Dn
AS Amount (Rs) 5829522
AS Number 93/PWD013-16/PDPMUKRFB/IHH/KSGD/217
TS Amount (Rs) 1780000
TS Number TS/2021-2022/2021/43456
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 31 Dec 2022
Coverage

Packages

No. Project Name Location View
1 KIIFB-2017/18-Improvements to Hill Highway Kolichal Cherupuzha road-KM0/000 to 30/377BM&BC in Kasaragod District-Shifting of utilities of WSS to Malom Kanhangad PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2023 Work completed Kanhangad PH Sn AE
25 May 2023 Work in progress Kanhangad PH Sn AE
23 May 2023 Work in progress Kanhangad PH Sn AE
19 May 2023 Work in progress Kanhangad PH Sn AE
15 May 2023 Work in progress Kanhangad PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/03/2022
Scheduled date of Completion of the Project 24 May 2022
Expected date of Completion 31/05/2023

Processing Dates

AS Date 28 Sep 2021
TS Date 01 Feb 2022

Other details