Jal Jeevan Mission (JJM)-Kannur District-Mayyil Panchayath - WSS to kolachery and adjoining panchayaths - Phase III - Reappropriation work - Laying Distribution System and providing FHTC's, Construction of 14LL GLSR tank at Padikunnu. -Pipeline Work
Jal Jeevan Mission (JJM)-Kannur District-Mayyil Panchayath - WSS to kolachery and adjoining panchayaths - Phase III - Reappropriation work - Laying Distribution System and providing FHTC's, Construction of 14LL GLSR tank at Padikunnu. -Pipeline Work
Project Code
KNRJJM102316027
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-01
Description
Jal Jeevan Mission (JJM)-Kannur District-Mayyil Panchayath - WSS to kolachery and adjoining panchayaths - Phase III - Reappropriation work - Laying Distribution System and providing FHTC's, Construction of 14LL GLSR tank at Padikunnu. -Pipeline Work
Jal Jeevan Mission (JJM)-Kannur District-Mayyil Panchayath - WSS to kolachery and adjoining panchayaths - Phase III - Reappropriation work - Laying Distribution System and providing FHTC's, Construction of 14LL GLSR tank at Padikunnu. -Pipeline Work
Kolachery PH Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
04 Jul 2025
Work in progress. 160 mm 10 Kg/Cm2-2718 m, 140 mm 10 Kg/Cm2-1222 m, 110 mm 10 Kg/Cm2- 3370 m, 90 mm 10 Kg/Cm2-5405 m, 75 mm 10 Kg/Cm2-3776 m, 63 mm 10 kg/Cm2- 639 m, FHTC- 384, HTC-40
Kolachery PH Sn AE
24 Jun 2025
Work in progress. 160 mm 10 Kg/Cm2-2718 m, 140 mm 10 Kg/Cm2-1184 m, 110 mm 10 Kg/Cm2- 3120 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3776 m, 63 mm 10 kg/Cm2- 639 m, FHTC- 379, HTC-19
Kolachery PH Sn AE
20 Jun 2025
Work in progress. 160 mm 10 Kg/Cm2-2718 m, 140 mm 10 Kg/Cm2-1184 m, 110 mm 10 Kg/Cm2- 3120 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3776 m, 63 mm 10 kg/Cm2- 639 m, FHTC- 359, HTC-21
Kolachery PH Sn AE
17 Jun 2025
Work in progress. 160 mm 10 Kg/Cm2-2718 m, 140 mm 10 Kg/Cm2-1184 m, 110 mm 10 Kg/Cm2- 3120 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3776 m, 63 mm 10 kg/Cm2- 639 m, FHTC- 324, HTC-21
Kolachery PH Sn AE
11 Jun 2025
Work in progress. 160 mm 10 Kg/Cm2-2718 m, 140 mm 10 Kg/Cm2-1184 m, 110 mm 10 Kg/Cm2- 3120 m, 90 mm 10 Kg/Cm2-5000 m, 75 mm 10 Kg/Cm2-3776 m, 63 mm 10 kg/Cm2- 639 m, FHTC- 324, HTC-9