| Project | PACKAGE III- SUPPLYING , LAYING , TESTING AND COMMISSIONING OF TRANSMISSION MAIN FROM WTP AT EDAKKANAM TO SERVICE RESERVOIRS IN 5 PANCHAYATHS |
|---|---|
| Project Code | KNRJJM022213306P3 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 11791 |
| TS Number | 9083/2023-2024 |
| Technical specification | Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 16/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Jul 2024 |
| Expected date of Completion | 31/12/2025 |
| TS Date | 16 Jul 2023 |
|---|---|
| Estimate Approval | 16 Jul 2023 |
| NIT Approval | 15 Jul 2023 |
| Tender Closing | 19 Aug 2023 |
| Technichal Pre-Qualification | 15 Jul 2023 |
| Price bid opening | 21 Aug 2023 |
| Workorder Date | 16 Sep 2023 |
|---|---|
| NA | 06 Oct 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 63% Completed
Total transmission main 49.767 km, in that pipe supplied is 39.622 km. 33.233 km pipe laying completed. Ambalapuzha steel bridge pier foundation earth work in progress.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta road (3.5km).700 m BM work completed,next stretch tarring to be in progress. Aythara-Goshala road 2300m (GSB+WMM) completed.LSGD road 2km tarring completed.
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 63% Completed
Total transmission main 49.767 km, in that pipe supplied is 39.622 km. 33.211 km pipe laying completed. Ambalapuzha steel bridge pier foundation earth work in progress.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta road (3.5km).700 m BM work completed,next stretch tarring to be in progress. Aythara-Goshala road 2200m (GSB+WMM) completed.LSGD road 2km tarring completed.