Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

PACKAGE III- SUPPLYING , LAYING , TESTING AND COMMISSIONING OF TRANSMISSION MAIN FROM WTP AT EDAKKANAM TO SERVICE RESERVOIRS IN 5 PANCHAYATHS

Project PACKAGE III- SUPPLYING , LAYING , TESTING AND COMMISSIONING OF TRANSMISSION MAIN FROM WTP AT EDAKKANAM TO SERVICE RESERVOIRS IN 5 PANCHAYATHS
Project Code KNRJJM022213306P3
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 11791
TS Number 9083/2023-2024
Technical specification Supplying, laying ,testing and commissioning of DI transmission main from proposed 32 mld WTP at Edakkanam to Service Reservoirs in 5 Panchayaths

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 16/10/2023
Scheduled date of Completion as per agreement 15 Jul 2024
Expected date of Completion 31/12/2025

Processing Dates

TS Date 16 Jul 2023
Estimate Approval 16 Jul 2023
NIT Approval 15 Jul 2023
Tender Closing 19 Aug 2023
Technichal Pre-Qualification 15 Jul 2023
Price bid opening 21 Aug 2023

Approval Dates

Workorder Date 16 Sep 2023
NA 06 Oct 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 05/01/2026

Work in progress | 63% Completed

Total transmission main 49.767 km, in that pipe supplied is 39.622 km. 33.233 km pipe laying completed. Ambalapuzha steel bridge pier foundation earth work in progress.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta road (3.5km).700 m BM work completed,next stretch tarring to be in progress. Aythara-Goshala road 2300m (GSB+WMM) completed.LSGD road 2km tarring completed.

Mattannur Project Sn 2 AE
Date: 30/12/2025

Work in progress | 63% Completed

Total transmission main 49.767 km, in that pipe supplied is 39.622 km. 33.211 km pipe laying completed. Ambalapuzha steel bridge pier foundation earth work in progress.Permission letter received from NHAI-Kozhikode on dated.12/08/25 for laying pipe lines (700mm Dia MS Casing pipe with 1No. 200mm dia DI pipe & 1No. 90mm PVC carrier pipe) across Chokli-Perngadi Road ( underpass of Thalassery- Mahe Bypass-NH-66 ) crossing at Ch.185+550,Kaviyoor LVUP by push through method.Road restoration work in progress . at valiyavelicham-cheeratta road (3.5km).700 m BM work completed,next stretch tarring to be in progress. Aythara-Goshala road 2200m (GSB+WMM) completed.LSGD road 2km tarring completed.