Project | Deposit 2022-23 - CWSS to Pulpally & Mullankolly - Providing water connection to Take A Break schme in Perikalloor bus station in Mullankolly GP |
---|---|
Project Code | WYDDEPO012313540P1 |
Type | Package |
Main Project | Deposit 2022-23 - CWSS to Pulpally & Mullankolly - Providing water connection to Take A Break schme in Perikalloor bus station in Mullankolly GP |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit 2022-23 - CWSS to Pulpally & Mullankolly - Providing water connection to Take A Break schme in Perikalloor bus station in Mullankolly GP |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 90000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/6641/2022_26_1_1 |
Technical specification | Providing water connection to Take A Break schme in Perikalloor bus station |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 15/02/2023 |
---|---|
Scheduled date of Completion as per agreement | 15 Mar 2023 |
Expected date of Completion | 15/03/2023 |
TS Date | 06 Feb 2023 |
---|---|
Estimate Approval | 06 Feb 2023 |
NIT Approval | 06 Feb 2023 |
Tender Closing | 13 Feb 2023 |
Technichal Pre-Qualification | 13 Feb 2023 |
Price bid opening | 14 Feb 2023 |
Workorder Date | 14 Feb 2023 |
---|---|
NA | 15 Feb 2023 |
Sulthan Bathery PH Dn EE |
Date: 23/02/2023 |
Work has been completed | 100% Completed
work completed.
Sulthan Bathery PH Dn EE |
Date: 18/02/2023 |
Work in progress | 25% Completed
work started.