| Project | RWSS to Muttil Zone II - Malakkad - Urgent inter connection work near Swargamkunnu WTP |
|---|---|
| Project Code | WYDGOK03229646P2 |
| Type | Package |
| Main Project | DRW 2022 - Urgent Interconnection works |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | RWSS to Muttil Zone II - Malakkad - Urgent inter connection work near Swargamkunnu WTP |
| Status | On-going |
| District | Wayanad |
| Executing Office | Sulthan Bathery Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 200000 |
| TS Number | TS/2022-2023/2022/12590 |
| Technical specification | interconnection work |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 05/05/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 31 Aug 2022 |
| Expected date of Completion | 31/08/2022 |
| TS Date | 20 Apr 2022 |
|---|---|
| Estimate Approval | 20 Apr 2022 |
| NIT Approval | 22 Apr 2022 |
| Tender Closing | 29 Apr 2022 |
| Sulthan Bathery PH Dn EE |
| Date: 30/10/2023 |
Work has started | 0% Completed
Work dropped as the same is done as part of State Plan work..
| Sulthan Bathery PH Dn EE |
| Date: 21/10/2023 |
Work has started | 0% Completed
to be re-tendered after recasting the estimate in PRICE-3.