JAL JEEVAN MISSION- 2021-22- WSS to Muthalamada Panchayath – construction of 6 LL OHSR, supplying, laying, testing, Commissioning and maintenance of CWPM, Supply & erection of RW, CW pump sets & Transformer, Construction of CW pump house, Supplying & laying distribution network & Providing FHTCs (1684 Nos) and PWD road restoration works
Project |
JAL JEEVAN MISSION- 2021-22- WSS to Muthalamada Panchayath – construction of 6 LL OHSR, supplying, laying, testing, Commissioning and maintenance of CWPM, Supply & erection of RW, CW pump sets & Transformer, Construction of CW pump house, Supplying & laying distribution network & Providing FHTCs (1684 Nos) and PWD road restoration works |
Project Code |
PKDJJM122012699 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JAL JEEVAN MISSION- 2021-22- WSS to Muthalamada Panchayath –construction of 6 LL OHSR, supplying, laying, testing, Commissioning and maintenance of CWPM, Supply & erection of RW, CW pump sets &Transformer, Construction of CW pump house, Supplying & layingdistribution network & Providing FHTCs (1684 Nos) and PWD roadrestoration works |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
280800000
|
AS Number |
GO(Rt)NO.777/2020/WRD/TVM |
TS Amount (Rs) |
260500000 |
TS Number |
TS/2021-2022/2021/40663 |
Total Bill Submitted (Rs) |
90260426 |
Total Bill Paid (Rs) |
90260426 |
Population Benefitted |
37060 |
Capacity in MLD |
|
Actual Project Completion Date |
23 Sep 2023 |
Coverage |
Muthalamada |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN MISSION- 2021-22- WSS to Muthalamada Panchayath – construction of 6 LL OHSR, supplying, laying, testing, Commissioning and maintenance of CWPM, Supply & erection of RW, CW pump sets & Transformer, Construction of CW pump house, Supplying & laying distribution network & Providing FHTCs (1684 Nos) and PWD road restoration works |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
6LL OHSR- painting work is completed, boundary wall completed,804 HTC provided/1684 nos. Various dia of pvc pipes and GI pipes are supplied at site.pump house painting completed,transformer installation work in progress, PTotal supply-110 km, Total laid- 118 km /out of 120km , 1.) 90 mm PN8 -25km supplied- 24286 m laid 2) 90 mm 8PN 10 kg-25km supplied and 15015 m laid 3)90 mm PN 12.50 kg-10714m laid 4)90mm PN 16 KG-14949 m Laid 5)125mm PN 10-518 m laid 6)125mm PN 12.50-1492 m laid 7)160mm PN8 -223 m laid 8)160mm PN 10-2278 m laid 9)160 PN mm 12.50-2009.50m laid 10)160mm PN 16-580M LAID 11)250mm DI-13867.00m laid 12)200 mm DI-4393 m laid 13)450mm DI-756.50 laid 14)80mm GI-3124m laid 15)100mm GI -116m laid 16)50mm GI-110m lai |
Chittur Project Dn - EE |
|
09 May 2024 |
6LL OHSR- painting work is completed, boundary wall completed,804 HTC provided/1684 nos. Various dia of pvc pipes and GI pipes are supplied at site.pump house painting completed,transformer installation work in progress, PTotal supply-110 km, Total laid- 118 km /out of 120km , 1.) 90 mm PN8 -25km supplied- 24286 m laid 2) 90 mm 8PN 10 kg-25km supplied and 15015 m laid 3)90 mm PN 12.50 kg-10714m laid 4)90mm PN 16 KG-14949 m Laid 5)125mm PN 10-518 m laid 6)125mm PN 12.50-1492 m laid 7)160mm PN8 -223 m laid 8)160mm PN 10-2278 m laid 9)160 PN mm 12.50-2009.50m laid 10)160mm PN 16-580M LAID 11)250mm DI-13867.00m laid 12)200 mm DI-4393 m laid 13)450mm DI-756.50 laid 14)80mm GI-3124m laid 15)100mm GI -116m laid 16)50mm GI-110m laid |
Chittur Project Dn - EE |
|
23 Apr 2024 |
6LL OHSR- painting work is completed, boundary wall completed,804 HTC provided/1684 nos. Various dia of pvc pipes and GI pipes are supplied at site.pump house painting completed,transformer installation work in progress, PTotal supply-110 km, Total laid- 118 km /out of 120km , 1.) 90 mm PN8 -25km supplied- 24286 m laid 2) 90 mm 8PN 10 kg-25km supplied and 15015 m laid 3)90 mm PN 12.50 kg-10714m laid 4)90mm PN 16 KG-14949 m Laid 5)125mm PN 10-518 m laid 6)125mm PN 12.50-1492 m laid 7)160mm PN8 -223 m laid 8)160mm PN 10-2278 m laid 9)160 PN mm 12.50-2009.50m laid 10)160mm PN 16-580M LAID 11)250mm DI-13867.00m laid 12)200 mm DI-4393 m laid 13)450mm DI-756.50 laid 14)80mm GI-3124m laid 15)100mm GI -116m laid 16)50mm GI-110m laid |
Chittur Project Dn - EE |
|
11 Apr 2024 |
Work in progress | 80% Completed | 11/04/2024
6LL OHSR- painting work is completed, boundary wall completed,804 HTC provided/1684 nos. Various dia of pvc pipes and GI pipes are supplied at site.pump house painting completed,transformer installation work in progress, PTotal supply-110 km, Total laid- 118 km /out of 120km , 1.) 90 mm PN8 -25km supplied- 24286 m laid 2) 90 mm 8PN 10 kg-25km supplied and 15015 m laid 3)90 mm PN 12.50 kg-10714m laid 4)90mm PN 16 KG-14949 m Laid 5)125mm PN 10-518 m laid 6)125mm PN 12.50-1492 m laid 7)160mm PN8 -223 m laid 8)160mm PN 10-2278 m laid 9)160 PN mm 12.50-2009.50m laid 10)160mm PN 16-580M LAID 11)250mm DI-13867.00m laid 12)200 mm DI-4393 m laid 13)450mm DI-756.50 laid 14)80mm GI-3124m laid 15)100mm GI -116m laid 16)50mm GI-110m laid |
Chittur Project Dn - EE |
|
05 Apr 2024 |
Work in progress | 80% Completed | 05/04/2024
6LL OHSR- painting work is completed, boundary wall completed,804 HTC provided/1684 nos. Various dia of pvc pipes and GI pipes are supplied at site.pump house painting completed,transformer installation work in progress, PTotal supply-110 km, Total laid- 118 km /out of 120km , 1.) 90 mm PN8 -25km supplied- 24286 m laid 2) 90 mm 8PN 10 kg-25km supplied and 15015 m laid 3)90 mm PN 12.50 kg-10714m laid 4)90mm PN 16 KG-14949 m Laid 5)125mm PN 10-518 m laid 6)125mm PN 12.50-1492 m laid 7)160mm PN8 -223 m laid 8)160mm PN 10-2278 m laid 9)160 PN mm 12.50-2009.50m laid 10)160mm PN 16-580M LAID 11)250mm DI-13867.00m laid 12)200 mm DI-4393 m laid 13)450mm DI-756.50 laid 14)80mm GI-3124m laid 15)100mm GI -116m laid 16)50mm GI-110m laid |
Chittur Project Dn - EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/09/2022 |
Scheduled date of Completion of the Project |
23 Sep 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
11 Jan 2022 |