DEPOSIT-Maravanthuruthu panchayath ward-1-Dismantling and Relaying of 63mm PVC Pipe at Vazhekkadu--Vallathara Culvert Portion-Pipeline Work
Project |
DEPOSIT-Maravanthuruthu panchayath ward-1-Dismantling and Relaying of 63mm PVC Pipe at Vazhekkadu--Vallathara Culvert Portion-Pipeline Work |
Project Code |
KTMDEPO022314363 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Maravanthuruthu panchayath ward-1-Dismantling and Relaying of 63mm PVC Pipe at Vazhekkadu--Vallathara Culvert Portion-Pipeline Work |
Status |
Completed |
District |
Kottayam |
Executing Office |
Vaikom Sn |
AS Amount (Rs) |
47100
|
AS Number |
TR - 59(E) 249 |
TS Amount (Rs) |
45900 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/1037/2022_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
500 |
Capacity in MLD |
45.00 |
Actual Project Completion Date |
13 Aug 2023 |
Coverage |
DEPOSIT-Maravanthuruthu panchayath ward-1-Dismantling and Relaying of 63mm PVC Pipe at Vazhekkadu--Vallathara Culvert Portion-Pipeline Work |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Maravanthuruthu panchayath ward-1-Dismantling and Relaying of 63mm PVC Pipe at Vazhekkadu--Vallathara Culvert Portion-Pipeline Work |
Vaikom Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jun 2023 |
WORK COMPLETED |
Kaduthuruthy Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
14/06/2023 |
Scheduled date of Completion of the Project |
13 Aug 2023 |
Expected date of Completion |
13/08/2023 |
Processing Dates
AS Date |
08 Feb 2023 |
TS Date |
12 Jun 2023 |