DEPOSIT-Jilla Panchayat-2022-23-Providing Water supply Scheme to Namattamkunnu ST Colony in Mullankolly GP-Pipeline Work

Project DEPOSIT-Jilla Panchayat-2022-23-Providing Water supply Scheme to Namattamkunnu ST Colony in Mullankolly GP-Pipeline Work
Project Code WYDDEPO022315055P1
Type Package
Main Project DEPOSIT-Jilla Panchayat-2022-23-Providing Water supply Scheme to Namattamkunnu ST Colony in Mullankolly GP-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Jilla Panchayat-2022-23-Providing Water supply Scheme to Namattamkunnu ST Colony in Mullankolly GP-Pipeline Work
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 1250000
TS Number TS/16923/2023_26_1_1
Technical specification Providing Water supply Scheme to Namattamkunnu ST Colony

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/11/2023
Scheduled date of Completion as per agreement 20 May 2024
Expected date of Completion 19/05/2024

Processing Dates

TS Date 27 Oct 2023
Estimate Approval 27 Oct 2023
NIT Approval 27 Oct 2023
Tender Closing 08 Nov 2023
Technichal Pre-Qualification 08 Nov 2023
Price bid opening 09 Nov 2023

Approval Dates

Workorder Date 20 Nov 2023
NA 21 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 04/05/2024

Work has been completed | 100% Completed

Work completed. Bill to be submitted..

Sulthan Bathery PH Dn EE
Date: 25/04/2024

Work in progress | 90% Completed

tank work completed and electrical work completed to pump house and power connection requred for KSEB .