JJM - Providing FHTC to Rural house holds in Vazhakkulam Panchayath Phase II,Part 5

Project JJM - Providing FHTC to Rural house holds in Vazhakkulam Panchayath Phase II,Part 5
Project Code EKMJJM08203026P2
Type Package
Main Project JJM - Providing FHTC to Rural house holds in Vazhakkulam Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-2021-Vazhakulam Panchayath in Ernakulam District Phase ll-part V - Extension of pipe line in ward no 13&16 and providing (Functional House Hold Tap Connections FHTC)
Status On-going
District Ernakulam
Executing Office Aluva JJM Section
Agreement Number
Agreement Date
TS Amount (Rs) 10000000
TS Number ORDER No. TS/2021-2022/2022/11600 Dated: 28-03-2022
Technical specification TS/2021-2022/2022/11600 Dated: 28-03-2022 Reg .No. 23999/2021-2022
Contractor M/S Andhyodaya (Mob: 9388607010)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/02/2022
Scheduled date of Completion as per agreement 31 Dec 2022
Expected date of Completion 30/06/2023

Processing Dates

TS Date 28 Mar 2022
Estimate Approval 28 Mar 2022
NIT Approval 28 Mar 2022
Tender Closing 05 Apr 2022
Price bid opening 07 Apr 2022

Approval Dates

Workorder Date 13 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattimattom - Kunnathunadu AE
Date: 18/05/2024

Work in progress | 95% Completed

final bill submitted - 422 FHTC given.

Pattimattom - Kunnathunadu AE
Date: 17/05/2024

Work in progress | 95% Completed

final bill submitted - 422 FHTC given.