| Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Pallikunnu Zone II |
|---|---|
| Project Code | KNRAMRUT122315858P1 |
| Type | Package |
| Main Project | AMRUT 1.0-Kannur Corporation-Pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Pallikunnu Zone II |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Pallikunnu Zone II |
| Status | On-going |
| District | Kannur |
| Executing Office | Kannur WS Sn 3 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 34600000 |
| TS Number | 23563/2023-24 |
| Technical specification | 90mm PVC 8kg/cm2 pipe ,110mm PVC 8kg/cm2 pipe ,160mm PVC 8kg/cm2 pipe |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 24/02/2024 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Apr 2024 |
| Expected date of Completion | 30/03/2024 |
| TS Date | 06 Jan 2024 |
|---|---|
| Estimate Approval | 01 Jan 2024 |
| NIT Approval | 06 Jan 2024 |
| Tender Closing | 12 Jan 2024 |
| Technichal Pre-Qualification | 06 Jan 2024 |
| Price bid opening | 13 Jan 2024 |
| Workorder Date | 29 Jan 2024 |
|---|---|
| NA | 14 Feb 2024 |
| Kannur PH Sn 3 AE |
| Date: 04/10/2025 |
Work has been completed | 100% Completed
Work has been completed,8 KM Pipe laid ,702 FHTC.
| Kannur PH Sn 3 AE |
| Date: 17/09/2025 |
Work has been completed | 100% Completed
Work has been completed,8 KM Pipe laid ,702 FHTC .