DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation.

Project DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation.
Project Code EKMDEPO11208806P1
Type Package
Main Project DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation.
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation.
Status On-going
District Ernakulam
Executing Office Kaloor WW Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 1060000
TS Number TS/2020-2021/2020/20572
Technical specification DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 31/08/2021
Scheduled date of Completion as per agreement 28 Sep 2021
Expected date of Completion 28/02/2023

Processing Dates

TS Date 27 Dec 2020
Estimate Approval 27 Dec 2020
NIT Approval 17 May 2021
Tender Closing 14 May 2021
Technichal Pre-Qualification 14 May 2021
Price bid opening 14 May 2021

Approval Dates

Workorder Date 07 Jun 2021
NA 31 Aug 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kaloor AE 2
Date: 30/04/2024

Work has been completed | 100% Completed

Bill submitted.

Kaloor AE 2
Date: 19/04/2024

Work has been completed | 100% Completed

Bill submitted.