Project | DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation. |
---|---|
Project Code | EKMDEPO11208806P1 |
Type | Package |
Main Project | DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation. |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation. |
Status | On-going |
District | Ernakulam |
Executing Office | Kaloor WW Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 1060000 |
TS Number | TS/2020-2021/2020/20572 |
Technical specification | DW-Kochi Corporation-Replacing the existing 100 mm AC/90 mm /63 mm PVC pipe by supplying and laying 110 mm PVC pipe (6 kg/cm2) 120 m at Kannanthodath road Kannanthodath 3 rd cross road and Govt high school road in Diiv no:34 (old)38 (new) of Kochi Corporation. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 31/08/2021 |
---|---|
Scheduled date of Completion as per agreement | 28 Sep 2021 |
Expected date of Completion | 28/02/2023 |
TS Date | 27 Dec 2020 |
---|---|
Estimate Approval | 27 Dec 2020 |
NIT Approval | 17 May 2021 |
Tender Closing | 14 May 2021 |
Technichal Pre-Qualification | 14 May 2021 |
Price bid opening | 14 May 2021 |
Workorder Date | 07 Jun 2021 |
---|---|
NA | 31 Aug 2021 |
Kaloor AE 2 |
Date: 30/04/2024 |
Work has been completed | 100% Completed
Bill submitted.
Kaloor AE 2 |
Date: 19/04/2024 |
Work has been completed | 100% Completed
Bill submitted.