Deposit Work-Balaramapuram Grama Panchayath- RWSS to Aruvipuram Zone providing Water supply line extension using 75mm PVC 8kg/cm2 at Karathala Kuzhivila to Puthrakkadavu Thembamuttam road in Resselpuram

Project Deposit Work-Balaramapuram Grama Panchayath- RWSS to Aruvipuram Zone providing Water supply line extension using 75mm PVC 8kg/cm2 at Karathala Kuzhivila to Puthrakkadavu Thembamuttam road in Resselpuram
Project Code TVMDEPO032210558
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit Work-Balaramapuram Grama Panchayath- RWSS to Aruvipuram Zone providing Water supply line extension using 75mm PVC 8kg/cm2 at Karathala Kuzhivila to Puthrakkadavu Thembamuttam road in Resselpuram
Status Completed
District Thiruvananthapuram
Executing Office Neyyattinkara WS Sn
AS Amount (Rs) 580000
AS Number 1000508/2022/4101
TS Amount (Rs) 580000
TS Number TS/2022-2023/2022/4101
Total Bill Submitted (Rs)
Total Bill Paid (Rs) 459864
Population Benefitted 500
Capacity in MLD 1.00
Actual Project Completion Date 04 Jul 2022
Coverage Water supply line extension using 75mm PVC 8kg/cm2 at Karathala Kuzhivila to Puthrakkadavu Thembamuttam road in Resselpuram

Packages

No. Project Name Location View
1 Deposit Work-Balaramapuram Grama Panchayath- RWSS to Aruvipuram Zone providing Water supply line extension using 75mm PVC 8kg/cm2 at Karathala Kuzhivila to Puthrakkadavu Thembamuttam road in Resselpuram Neyyattinkara WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Dec 2022 Work Completed. Bill paid.459864 Neyyattinkara AE
19 Dec 2022 Work completed Neyyattinkara AE
17 Dec 2022 Work completed Neyyattinkara AE
15 Dec 2022 Work completed Neyyattinkara AE
14 Dec 2022 Work completed Neyyattinkara AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/05/2022
Scheduled date of Completion of the Project 20 Jun 2022
Expected date of Completion 20/06/2022

Processing Dates

AS Date 31 Mar 2022
TS Date 07 Apr 2022

Other details

Project Officers View