Jal jeevan Mission 2021-22-Design,Construction and shifitng of quality control district lab Wayanad for NABL accreditaion-Civil and Electrical works
Project |
Jal jeevan Mission 2021-22-Design,Construction and shifitng of quality control district lab Wayanad for NABL accreditaion-Civil and Electrical works |
Project Code |
WYDJJM09218516 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal jeevan Mission 2021-22-Design,Construction and shifitng of quality control district lab Wayanad for NABL accreditaion-Civil and Electrical works |
Status |
On-going |
District |
Wayanad |
Executing Office |
Wayanad QC Sn |
AS Amount (Rs) |
838600000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
9607000 |
TS Number |
TS/2021-2022/2021/28902 for Civil work TS/2021-2022/2021/30009 for Electrical work |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal jeevan Mission 2021-22-Design,Construction and shifitng of quality control district lab Wayanad for NABL accreditaion-Civil and Electrical works |
Wayanad QC Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Nov 2022 |
Electrical,tile work and plumbing are in progress |
Kozhikode QC Sub Dn AEE |
|
18 Oct 2022 |
Plastering work completed |
Kozhikode QC Sub Dn AEE |
|
01 Sep 2022 |
Shuttering and centering roof slab of the stair room are progressing. |
Kozhikode QC Sub Dn AEE |
|
11 Mar 2022 |
Plinth beam wok is in progress |
Kozhikode QC Sub Dn AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/09/2021 |
Scheduled date of Completion of the Project |
07 Jun 2022 |
Expected date of Completion |
07/06/2022 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
21 Oct 2021 |