Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Project Code
PKDJJM092110519
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jal Jeevan Mission- 2021-22 Augmentation of CWSS to Kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Status
On-going
District
Palakkad
Executing Office
Chittur Project Dn
AS Amount (Rs)
165000000
AS Number
Go(Rt) No.489/2021/WRD DATED18.09.2021
TS Amount (Rs)
164200000
TS Number
TS/2021-22/2021/38223 DATED 26.11.2021
Total Bill Submitted (Rs)
136005489
Total Bill Paid (Rs)
136005489
Population Benefitted
29587
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
KOLLENGODE Grama Panchayath
Packages
No.
Project Name
Location
View
1
Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Project Division Chittur
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
26 May 2023
Work has been completed | 100% Completed | 26/05/2023
Total-69km laid / OUT OF 69 KM FHTC-1514 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates
Chittur Project Dn - AE 4
19 May 2023
Work in progress | 98% Completed | 19/05/2023
Total-67.894 Km laid / OUT OF 69 KM FHTC-1489 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates
Chittur Project Dn - AE 4
11 May 2023
Work in progress | 98% Completed | 11/05/2023
Total-67.894 Km laid / OUT OF 69 KM FHTC-1464Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates
Chittur Project Dn - AE 4
05 May 2023
Work in progress | 97% Completed | 05/05/2023
69.11km pipe total supplied Total-67.00 Km laid / OUT OF 69 KM FHTC-1408 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30449 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7077.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89494 m laid 8)150MM GI -24.70 M 9)100MM GI-55.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates
Chittur Project Dn - AE 4
28 Apr 2023
Work in progress | 91% Completed | 28/04/2023
69.11km pipe total supplied Total-63.00 Km laid / OUT OF 69 KM FHTC-1347 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30287 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7032.80m laid 4).200 mm DI-5427.50 m supplied-5176 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89027 m laid 8)150MM GI -24.70 M 9)100MM GI-55.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates