Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network

Project Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Project Code PKDJJM092110519
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 2021-22 Augmentation of CWSS to Kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 165000000
AS Number Go(Rt) No.489/2021/WRD DATED18.09.2021
TS Amount (Rs) 164200000
TS Number TS/2021-22/2021/38223 DATED 26.11.2021
Total Bill Submitted (Rs) 136005489
Total Bill Paid (Rs) 136005489
Population Benefitted 29587
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage KOLLENGODE Grama Panchayath

Packages

No. Project Name Location View
1 Jal Jeevan Mission- 2021-22 Augmentation of CWSS to kollengode and adjoining Panchayaths-Supplying ,Laying testing commissioning and maintanance of 2442m DI Clear Water Gravity Main and distribution system using DI and HDPE pipes and providing FHTC s including topographichal survey of pipe line network using DGPS instrument and design the pipeline network Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 May 2023 Work has been completed | 100% Completed | 26/05/2023 Total-69km laid / OUT OF 69 KM FHTC-1514 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates Chittur Project Dn - AE 4
19 May 2023 Work in progress | 98% Completed | 19/05/2023 Total-67.894 Km laid / OUT OF 69 KM FHTC-1489 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates Chittur Project Dn - AE 4
11 May 2023 Work in progress | 98% Completed | 11/05/2023 Total-67.894 Km laid / OUT OF 69 KM FHTC-1464Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30736 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7155.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89908 m laid 8)150MM GI -84.70 M 9)100MM GI-110.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates Chittur Project Dn - AE 4
05 May 2023 Work in progress | 97% Completed | 05/05/2023 69.11km pipe total supplied Total-67.00 Km laid / OUT OF 69 KM FHTC-1408 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30449 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7077.80 m laid 4).200 mm DI-5427.50 m supplied-5182 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89494 m laid 8)150MM GI -24.70 M 9)100MM GI-55.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates Chittur Project Dn - AE 4
28 Apr 2023 Work in progress | 91% Completed | 28/04/2023 69.11km pipe total supplied Total-63.00 Km laid / OUT OF 69 KM FHTC-1347 Out of 4113 nos 1).90 mm HDPE-33780 M supplied- 30287 m laid 2).140mm HDPE-4945 m supplied-4555.20 m laid 3) 160 mm HDPE-7315 m supplied-7032.80m laid 4).200 mm DI-5427.50 m supplied-5176 m laid 5).250 mm DI -1908 m supplied-1908m laid 6).300 mm DI -2755.50 M supplied-2809m laid 7)110mm HDPE 12980 m supplied -89027 m laid 8)150MM GI -24.70 M 9)100MM GI-55.70M 10)80MM GI-9.45M 11)125MM GI-6.90M View all updates Chittur Project Dn - AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/02/2022
Scheduled date of Completion of the Project 09 Feb 2023
Expected date of Completion 30/04/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 26 Nov 2021

Other details

Project Officers View