DEPOSIT CWSS to Panavoor ,Pullampara and Vembayam- Nedumangadu Block, Panchayath- Providing pipe line extension Ayiruppara, Elankathara Cheeranikkara-Katta, Vettinad-Mandapam and Mozhinada Podiyankonam in Vembayam Panchayath
Project |
DEPOSIT CWSS to Panavoor ,Pullampara and Vembayam- Nedumangadu Block, Panchayath- Providing pipe line extension Ayiruppara, Elankathara Cheeranikkara-Katta, Vettinad-Mandapam and Mozhinada Podiyankonam in Vembayam Panchayath |
Project Code |
TVMDEPO092315042 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT CWSS to Panavoor ,Pullampara and Vembayam- Nedumangadu Block, Panchayath- Providing pipe line extension Ayiruppara, Elankathara Cheeranikkara-Katta, Vettinad-Mandapam and Mozhinada Podiyankonam in Vembayam Panchayath |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kallara Sn |
AS Amount (Rs) |
2048600
|
AS Number |
8/2022 |
TS Amount (Rs) |
2004155 |
TS Number |
5373/2023-2024 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
31 Mar 2024 |
Coverage |
Ayiruppara, Elankathara Cheeranikkara-Katta, Vettinad-Mandapam and Mozhinada Podiyankonam in Vembayam Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT CWSS to Panavoor ,Pullampara and Vembayam- Nedumangadu Block, Panchayath- Providing pipe line extension Ayiruppara, Elankathara Cheeranikkara-Katta, Vettinad-Mandapam and Mozhinada Podiyankonam in Vembayam Panchayath |
Kallara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 May 2024 |
ongoing |
Kallara AE |
|
03 May 2024 |
ongoing |
Kallara AE |
|
03 May 2024 |
ongoing |
Kallara AE |
|
29 Apr 2024 |
ongoing |
Kallara AE |
|
20 Apr 2024 |
work ongoing |
Kallara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/09/2023 |
Scheduled date of Completion of the Project |
24 Dec 2023 |
Expected date of Completion |
28/02/2024 |
Processing Dates
AS Date |
31 May 2023 |
TS Date |
06 Jun 2023 |