JAL JEEVAN MISSION - Pipe line extension,Replacement of AC pipes, Augmentation of WTP and providing FHTC in Chithara panchayath - Phase II

Project JAL JEEVAN MISSION - Pipe line extension,Replacement of AC pipes, Augmentation of WTP and providing FHTC in Chithara panchayath - Phase II
Project Code KLMJJM08204177
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Pipe line extension,Replacement of AC pipes, Augmentation of WTP and providing FHTC
Status On-going
District Kollam
Executing Office Madathara Sn
AS Amount (Rs) 264300000
AS Number G.O.(Rt)No.541/2020/WRD
TS Amount (Rs) 260040000
TS Number TS/2021-2022/2020/20404
Total Bill Submitted (Rs) 182368859
Total Bill Paid (Rs) 182368859
Population Benefitted 6100
Capacity in MLD 0.00
Actual Project Completion Date 31 Dec 2021
Coverage Chithara Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION - Pipe line extension,Replacement of AC pipes, Augmentation of WTP and providing FHTC in Chithara panchayath - Phase II Madathara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Dec 2023 5525/8236 connections provided in various wards and work are progressing Madathara PH Sn - AE
30 Nov 2023 5293/8236 connections provided in various wards and work are progressing Madathara PH Sn - AE
12 Oct 2023 5066/8236 connections provided in various wards and pipe line extension work are progressing Madathara PH Sn - AE
06 Jul 2023 4837/8236 connections provided in various wards and pipe line extension work are progressing Madathara PH Sn - AE
27 Jun 2023 4828/8236 connections provided in various wards and pipe line extension work are progressing Madathara PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/02/2021
Scheduled date of Completion of the Project 31 Dec 2021
Expected date of Completion 15/12/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 18 Sep 2020